Roads & HighwaysIPM · Central Project#619217

4L of Haridwar-Nagina section from km. 0.00 to km. 71.614 of NH-74

Ministry of Road Transport & HighwaysUttarakhand
Revised Cost: ₹1622 CrUtilization: 95.4%

Original Cost

₹1659 Cr

Baseline estimate

On budget

Revised Cost

₹1622 Cr

Latest approved cost

Expenditure

₹1549 Cr

Spent to date

Utilization

95.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹74 Cr

Budget left

Budget Utilization

95.4%
0%25%50%75%100%

Spent

₹1549 Cr

Remaining

₹74 Cr

Total

₹1622 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

22/07/2020

Revised Completion

13/10/2026

Completed

Project Details

Project Code619217
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateUttarakhand
Data Month2026-08

Financial Summary

Original Cost₹1659 Cr
Revised Cost₹1622 Cr
Expenditure₹1549 Cr
Original End Date22/07/2020
Revised Date13/10/2026

Project Intelligence

Project is within original budget of ₹1659 Cr — no cost escalation recorded.

Expenditure stands at ₹1549 Cr, which is 95.4% of the revised project cost.

Remaining budget: ₹74 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Haridwar-Nagina section from km. 0.00 to km. 71.614 of NH-74 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1659.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Haridwar-Nagina section from km. 0.00 to km. 71.614 of NH-74"?
4L of Haridwar-Nagina section from km. 0.00 to km. 71.614 of NH-74 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹1659 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1659 Cr and has been revised to ₹1622 Cr — a cost overrun of -2.2%. Expenditure to date: ₹1549 Cr (95.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Haridwar-Nagina section from km. 0.00 to km. 71.614 of is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619217. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Haridwar-Nagina section from km. 0.00 to km. 71.614 of is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.