Roads & HighwaysIPM · Central Project +6.7% overrun#619317

4L of Hajipur-Muzaffarpur Section of the existing NH-77 from Km. 0000 Ramashish Chowk to Km. 46300 and new bypass starting at Km. 46300 and connecting NH-28 of E-W Corridor at Km. 515045

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹2907 CrUtilization: 74.3%Overrun: +₹184 Cr

Original Cost

₹2723 Cr

Baseline estimate

+7% overrun

Revised Cost

₹2907 Cr

Latest approved cost

Expenditure

₹2161 Cr

Spent to date

Utilization

74.3%

Of revised budget

Escalated

Cost Status

+6.7%

+₹184 Cr increase

Remaining

₹746 Cr

Budget left

Budget Utilization

74.3%
0%25%50%75%100%

Spent

₹2161 Cr

Remaining

₹746 Cr

Total

₹2907 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2723 Cr

Revised Cost

₹2907 Cr

Increase

+₹184 Cr

Escalation

+6.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

06/02/2013

Revised Completion

31/10/2026

Completed

Project Details

Project Code619317
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹2723 Cr
Revised Cost₹2907 Cr
Expenditure₹2161 Cr
Original End Date06/02/2013
Revised Date31/10/2026

Project Intelligence

Cost has increased by ₹184 Cr (6.7%) from the original estimate of ₹2723 Cr.

Expenditure stands at ₹2161 Cr, which is 74.3% of the revised project cost.

Remaining budget: ₹746 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Hajipur-Muzaffarpur Section of the existing NH-77 from Km. 0000 Ramashish Chowk to Km. 46300 and new bypass starting at Km. 46300 and connecting NH-28 of E-W Corridor at Km. 515045 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2723.00 Cr, later revised to ₹2906.78 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Hajipur-Muzaffarpur Section of the existing NH-77 from Km. 0000 Ramashish"?
4L of Hajipur-Muzaffarpur Section of the existing NH-77 from Km. 0000 Ramashish Chowk to Km. 46300 and new bypass starting at Km. 46300 and connecting NH-28 of E-W Corridor at Km. 515045 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹2723 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2723 Cr and has been revised to ₹2907 Cr — a cost overrun of +6.7%. Expenditure to date: ₹2161 Cr (74.3% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Hajipur-Muzaffarpur Section of the existing NH-77 fro is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619317. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Hajipur-Muzaffarpur Section of the existing NH-77 fro is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.