bypass starting at Km. 46300 and connecting NH-28 of E-W Corridor at Km. 515045
Original Cost
₹2723 Cr
Baseline estimate
Revised Cost
₹2907 Cr
Latest approved cost
Expenditure
₹27 Cr
Spent to date
Utilization
0.9%
Of revised cost
Cost Overrun
+6.7%
+₹184 Cr
Remaining
₹2880 Cr
Budget left
Spent
₹27 Cr
Remaining
₹2880 Cr
Total
₹2907 Cr
0.9%
Utilized
Original Cost
₹2723 Cr
Revised Cost
₹2907 Cr
Increase
+₹184 Cr
Escalation
+6.7%
Project Approved
Construction / Implementation
Original End Date
2013-02-06
Revised Completion
2026-05-31
Completed
Cost has increased by ₹184 Cr (6.7%) from the original estimate of ₹2723 Cr.
Expenditure stands at ₹27 Cr, which is 0.9% of the revised project cost.
Remaining budget: ₹2880 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.