Original Cost
₹1003 Cr
Baseline estimate
Revised Cost
₹994 Cr
Latest approved cost
Expenditure
₹600 Cr
Spent to date
Utilization
60.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹394 Cr
Budget left
Spent
₹600 Cr
Remaining
₹394 Cr
Total
₹994 Cr
Project Approved
Construction / Implementation
Original End Date
21/06/2025
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹1003 Cr — no cost escalation recorded.
Expenditure stands at ₹600 Cr, which is 60.3% of the revised project cost.
Remaining budget: ₹394 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.