Original Cost
₹1103 Cr
Baseline estimate
Revised Cost
₹770 Cr
Latest approved cost
Expenditure
₹94 Cr
Spent to date
Utilization
12.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹677 Cr
Budget left
Spent
₹94 Cr
Remaining
₹677 Cr
Total
₹770 Cr
Project Approved
Construction / Implementation
Original End Date
17/08/2027
Revised Completion
08/05/2027
Completed
Project is within original budget of ₹1103 Cr — no cost escalation recorded.
Expenditure stands at ₹94 Cr, which is 12.2% of the revised project cost.
Remaining budget: ₹677 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.