Roads & HighwaysIPM · Central Project#618962

4L of Budhni to Shahganj Bypass End Package-III of NH-146B from Km. 73.750 to Km. 102.000

Ministry of Road Transport & HighwaysMadhya Pradesh
Revised Cost: ₹770 CrUtilization: 25.6%

Original Cost

₹1103 Cr

Baseline estimate

On budget

Revised Cost

₹770 Cr

Latest approved cost

Expenditure

₹197 Cr

Spent to date

Utilization

25.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹573 Cr

Budget left

Budget Utilization

25.6%
0%25%50%75%100%

Spent

₹197 Cr

Remaining

₹573 Cr

Total

₹770 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

17/08/2027

Revised Completion

17/08/2027

Completed

Project Details

Project Code618962
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMadhya Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1103 Cr
Revised Cost₹770 Cr
Expenditure₹197 Cr
Original End Date17/08/2027
Revised Date17/08/2027

Project Intelligence

Project is within original budget of ₹1103 Cr — no cost escalation recorded.

Expenditure stands at ₹197 Cr, which is 25.6% of the revised project cost.

Remaining budget: ₹573 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of Budhni to Shahganj Bypass End Package-III of NH-146B from Km. 73.750 to Km. 102.000 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1103.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of Budhni to Shahganj Bypass End Package-III of NH-146B from Km. 73.750 to Km"?
4L of Budhni to Shahganj Bypass End Package-III of NH-146B from Km. 73.750 to Km. 102.000 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹1103 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1103 Cr and has been revised to ₹770 Cr — a cost overrun of -30.2%. Expenditure to date: ₹197 Cr (25.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of Budhni to Shahganj Bypass End Package-III of NH-146B f is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618962. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Budhni to Shahganj Bypass End Package-III of NH-146B f is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.