4L of Budhni to Shahganj Bypass End Package-III of NH-146B from Km. 73.750 to Km. 102.000
Original Cost
₹1103 Cr
Baseline estimate
Revised Cost
₹770 Cr
Latest approved cost
Expenditure
₹197 Cr
Spent to date
Utilization
25.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹573 Cr
Budget left
Budget Utilization
25.6%Spent
₹197 Cr
Remaining
₹573 Cr
Total
₹770 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
17/08/2027
Revised Completion
17/08/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1103 Cr — no cost escalation recorded.
Expenditure stands at ₹197 Cr, which is 25.6% of the revised project cost.
Remaining budget: ₹573 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L of Budhni to Shahganj Bypass End Package-III of NH-146B from Km. 73.750 to Km. 102.000 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1103.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L of Budhni to Shahganj Bypass End Package-III of NH-146B from Km. 73.750 to Km"?
- 4L of Budhni to Shahganj Bypass End Package-III of NH-146B from Km. 73.750 to Km. 102.000 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹1103 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1103 Cr and has been revised to ₹770 Cr — a cost overrun of -30.2%. Expenditure to date: ₹197 Cr (25.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L of Budhni to Shahganj Bypass End Package-III of NH-146B f is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618962. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Budhni to Shahganj Bypass End Package-III of NH-146B f is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.