Original Cost
₹1445 Cr
Baseline estimate
Revised Cost
₹1554 Cr
Latest approved cost
Expenditure
₹653 Cr
Spent to date
Utilization
42.0%
Of revised budget
Cost Status
+7.5%
+₹109 Cr increase
Remaining
₹901 Cr
Budget left
Spent
₹653 Cr
Remaining
₹901 Cr
Total
₹1554 Cr
Original Cost
₹1445 Cr
Revised Cost
₹1554 Cr
Increase
+₹109 Cr
Escalation
+7.5%
Project Approved
Construction / Implementation
Original End Date
11/12/2025
Revised Completion
31/08/2026
Completed
Cost has increased by ₹109 Cr (7.5%) from the original estimate of ₹1445 Cr.
Expenditure stands at ₹653 Cr, which is 42.0% of the revised project cost.
Remaining budget: ₹901 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.