Original Cost
₹698 Cr
Baseline estimate
Revised Cost
₹736 Cr
Latest approved cost
Expenditure
₹418 Cr
Spent to date
Utilization
56.9%
Of revised budget
Cost Status
+5.4%
+₹38 Cr increase
Remaining
₹317 Cr
Budget left
Spent
₹418 Cr
Remaining
₹317 Cr
Total
₹736 Cr
Original Cost
₹698 Cr
Revised Cost
₹736 Cr
Increase
+₹38 Cr
Escalation
+5.4%
Project Approved
Construction / Implementation
Original End Date
24/09/2022
Revised Completion
Completed
Cost has increased by ₹38 Cr (5.4%) from the original estimate of ₹698 Cr.
Expenditure stands at ₹418 Cr, which is 56.9% of the revised project cost.
Remaining budget: ₹317 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.