4L of Bal Works of Mahuva to Kagvadar from 100.450 Km. to 140.470 Km. of NH-8E Pkg- III
Original Cost
₹603 Cr
Baseline estimate
Revised Cost
₹628 Cr
Latest approved cost
Expenditure
₹624 Cr
Spent to date
Utilization
99.4%
Of revised budget
Cost Status
+4.2%
+₹25 Cr increase
Remaining
₹4 Cr
Budget left
Budget Utilization
99.4%Spent
₹624 Cr
Remaining
₹4 Cr
Total
₹628 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹603 Cr
Revised Cost
₹628 Cr
Increase
+₹25 Cr
Escalation
+4.2%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
23/09/2022
Revised Completion
17/01/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹25 Cr (4.2%) from the original estimate of ₹603 Cr.
Expenditure stands at ₹624 Cr, which is 99.4% of the revised project cost.
Remaining budget: ₹4 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L of Bal Works of Mahuva to Kagvadar from 100.450 Km. to 140.470 Km. of NH-8E Pkg- III is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹603.00 Cr, later revised to ₹628.49 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L of Bal Works of Mahuva to Kagvadar from 100.450 Km. to 140.470 Km. of NH-8E "?
- 4L of Bal Works of Mahuva to Kagvadar from 100.450 Km. to 140.470 Km. of NH-8E Pkg- III is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹603 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹603 Cr and has been revised to ₹628 Cr — a cost overrun of +4.2%. Expenditure to date: ₹624 Cr (99.4% of revised cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- 4L of Bal Works of Mahuva to Kagvadar from 100.450 Km. to 1 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619147. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of Bal Works of Mahuva to Kagvadar from 100.450 Km. to 1 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.