Roads & HighwaysIPM · Central Project +40.1% overrun#619073

4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote section of NH-648 Old NH-207 [Bangalore Ring Road Pkg 2]

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹1847 CrUtilization: 73.7%Overrun: +₹529 Cr

Original Cost

₹1318 Cr

Baseline estimate

+40% overrun

Revised Cost

₹1847 Cr

Latest approved cost

Expenditure

₹1360 Cr

Spent to date

Utilization

73.7%

Of revised budget

Escalated

Cost Status

+40.1%

+₹529 Cr increase

Remaining

₹486 Cr

Budget left

Budget Utilization

73.7%
0%25%50%75%100%

Spent

₹1360 Cr

Remaining

₹486 Cr

Total

₹1847 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1318 Cr

Revised Cost

₹1847 Cr

Increase

+₹529 Cr

Escalation

+40.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

21/02/2023

Revised Completion

30/09/2026

Completed

Project Details

Project Code619073
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹1318 Cr
Revised Cost₹1847 Cr
Expenditure₹1360 Cr
Original End Date21/02/2023
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹529 Cr (40.1%) from the original estimate of ₹1318 Cr.

Expenditure stands at ₹1360 Cr, which is 73.7% of the revised project cost.

Remaining budget: ₹486 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote section of NH-648 Old NH-207 [Bangalore Ring Road Pkg 2] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1318.00 Cr, later revised to ₹1846.52 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote section of NH-648 Ol"?
4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote section of NH-648 Old NH-207 [Bangalore Ring Road Pkg 2] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹1318 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1318 Cr and has been revised to ₹1847 Cr — a cost overrun of +40.1%. Expenditure to date: ₹1360 Cr (73.7% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote s is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619073. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote s is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.