4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote section of NH-648 Old NH-207 [Bangalore Ring Road Pkg 2]
Original Cost
₹1318 Cr
Baseline estimate
Revised Cost
₹1847 Cr
Latest approved cost
Expenditure
₹1360 Cr
Spent to date
Utilization
73.7%
Of revised budget
Cost Status
+40.1%
+₹529 Cr increase
Remaining
₹486 Cr
Budget left
Budget Utilization
73.7%Spent
₹1360 Cr
Remaining
₹486 Cr
Total
₹1847 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1318 Cr
Revised Cost
₹1847 Cr
Increase
+₹529 Cr
Escalation
+40.1%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
21/02/2023
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹529 Cr (40.1%) from the original estimate of ₹1318 Cr.
Expenditure stands at ₹1360 Cr, which is 73.7% of the revised project cost.
Remaining budget: ₹486 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote section of NH-648 Old NH-207 [Bangalore Ring Road Pkg 2] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1318.00 Cr, later revised to ₹1846.52 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote section of NH-648 Ol"?
- 4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote section of NH-648 Old NH-207 [Bangalore Ring Road Pkg 2] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹1318 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1318 Cr and has been revised to ₹1847 Cr — a cost overrun of +40.1%. Expenditure to date: ₹1360 Cr (73.7% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote s is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619073. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote s is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.