Roads & HighwaysIPM · Central Project#618588

4L Mitigation Measure structures on CH/MH Border to Wainganga Bridge Section of NH-6 New NH-53

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹469 CrUtilization: 99.0%

Original Cost

₹540 Cr

Baseline estimate

On budget

Revised Cost

₹469 Cr

Latest approved cost

Expenditure

₹464 Cr

Spent to date

Utilization

99.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹5 Cr

Budget left

Budget Utilization

99.0%
0%25%50%75%100%

Spent

₹464 Cr

Remaining

₹5 Cr

Total

₹469 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

07/11/2023

Revised Completion

31/10/2026

Completed

Project Details

Project Code618588
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹540 Cr
Revised Cost₹469 Cr
Expenditure₹464 Cr
Original End Date07/11/2023
Revised Date31/10/2026

Project Intelligence

Project is within original budget of ₹540 Cr — no cost escalation recorded.

Expenditure stands at ₹464 Cr, which is 99.0% of the revised project cost.

Remaining budget: ₹5 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L Mitigation Measure structures on CH/MH Border to Wainganga Bridge Section of NH-6 New NH-53 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹540.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L Mitigation Measure structures on CH/MH Border to Wainganga Bridge Section of "?
4L Mitigation Measure structures on CH/MH Border to Wainganga Bridge Section of NH-6 New NH-53 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹540 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹540 Cr and has been revised to ₹469 Cr — a cost overrun of -13.2%. Expenditure to date: ₹464 Cr (99.0% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L Mitigation Measure structures on CH/MH Border to Waingang is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618588. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Mitigation Measure structures on CH/MH Border to Waingang is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.