4L from Mathura Bypass Start at Existing Km. 154.20 of NH-44 to Gaju Village at Km 32.982 of NH-530B Pkg-IB
Original Cost
₹1722 Cr
Baseline estimate
Revised Cost
₹1821 Cr
Latest approved cost
Expenditure
₹1050 Cr
Spent to date
Utilization
57.7%
Of revised budget
Cost Status
+5.7%
+₹99 Cr increase
Remaining
₹771 Cr
Budget left
Budget Utilization
57.7%Spent
₹1050 Cr
Remaining
₹771 Cr
Total
₹1821 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1722 Cr
Revised Cost
₹1821 Cr
Increase
+₹99 Cr
Escalation
+5.7%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/03/2025
Revised Completion
01/07/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹99 Cr (5.7%) from the original estimate of ₹1722 Cr.
Expenditure stands at ₹1050 Cr, which is 57.7% of the revised project cost.
Remaining budget: ₹771 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L from Mathura Bypass Start at Existing Km. 154.20 of NH-44 to Gaju Village at Km 32.982 of NH-530B Pkg-IB is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1722.00 Cr, later revised to ₹1820.77 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L from Mathura Bypass Start at Existing Km. 154.20 of NH-44 to Gaju Village at "?
- 4L from Mathura Bypass Start at Existing Km. 154.20 of NH-44 to Gaju Village at Km 32.982 of NH-530B Pkg-IB is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹1722 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1722 Cr and has been revised to ₹1821 Cr — a cost overrun of +5.7%. Expenditure to date: ₹1050 Cr (57.7% of revised cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- 4L from Mathura Bypass Start at Existing Km. 154.20 of NH-44 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618864. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L from Mathura Bypass Start at Existing Km. 154.20 of NH-44 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.