Roads & HighwaysIPM · Central Project#618570

4L Elevated Highway and at grade improvements at Gopalganj Town from Km. 384.000 to Km. 386.750 on NH-27

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹249 CrUtilization: 90.6%

Original Cost

₹326 Cr

Baseline estimate

On budget

Revised Cost

₹249 Cr

Latest approved cost

Expenditure

₹225 Cr

Spent to date

Utilization

90.6%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹23 Cr

Budget left

Budget Utilization

90.6%
0%25%50%75%100%

Spent

₹225 Cr

Remaining

₹23 Cr

Total

₹249 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/08/2024

Revised Completion

15/04/2026

Completed

Project Details

Project Code618570
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-05

Financial Summary

Original Cost₹326 Cr
Revised Cost₹249 Cr
Expenditure₹225 Cr
Original End Date31/08/2024
Revised Date15/04/2026

Project Intelligence

Project is within original budget of ₹326 Cr — no cost escalation recorded.

Expenditure stands at ₹225 Cr, which is 90.6% of the revised project cost.

Remaining budget: ₹23 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L Elevated Highway and at grade improvements at Gopalganj Town from Km. 384.000 to Km. 386.750 on NH-27 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹326.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L Elevated Highway and at grade improvements at Gopalganj Town from Km. 384.000"?
4L Elevated Highway and at grade improvements at Gopalganj Town from Km. 384.000 to Km. 386.750 on NH-27 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹326 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹326 Cr and has been revised to ₹249 Cr — a cost overrun of -23.6%. Expenditure to date: ₹225 Cr (90.6% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
4L Elevated Highway and at grade improvements at Gopalganj T is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618570. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Elevated Highway and at grade improvements at Gopalganj T is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.