Roads & HighwaysIPM · Central Project#618792

4L Bhiwani-Hansi road section of NH-148B

Ministry of Road Transport & HighwaysHaryana
Revised Cost: ₹1144 CrUtilization: 43.1%

Original Cost

₹1330 Cr

Baseline estimate

On budget

Revised Cost

₹1144 Cr

Latest approved cost

Expenditure

₹493 Cr

Spent to date

Utilization

43.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹651 Cr

Budget left

Budget Utilization

43.1%
0%25%50%75%100%

Spent

₹493 Cr

Remaining

₹651 Cr

Total

₹1144 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

17/12/2025

Revised Completion

19/11/2026

Completed

Project Details

Project Code618792
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateHaryana
Data Month2026-08

Financial Summary

Original Cost₹1330 Cr
Revised Cost₹1144 Cr
Expenditure₹493 Cr
Original End Date17/12/2025
Revised Date19/11/2026

Project Intelligence

Project is within original budget of ₹1330 Cr — no cost escalation recorded.

Expenditure stands at ₹493 Cr, which is 43.1% of the revised project cost.

Remaining budget: ₹651 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L Bhiwani-Hansi road section of NH-148B is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1330.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L Bhiwani-Hansi road section of NH-148B"?
4L Bhiwani-Hansi road section of NH-148B is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Haryana. Original cost: ₹1330 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1330 Cr and has been revised to ₹1144 Cr — a cost overrun of -14%. Expenditure to date: ₹493 Cr (43.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L Bhiwani-Hansi road section of NH-148B is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618792. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Bhiwani-Hansi road section of NH-148B is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.