4L Behsuma at Km 39.250 Ex. Km 39240 To Bijnor at Km 78.810 Ex. Km 86590 Design Length 39.560 Km of NH-119 Pkg-II
Original Cost
₹2158 Cr
Baseline estimate
Revised Cost
₹2553 Cr
Latest approved cost
Expenditure
₹1236 Cr
Spent to date
Utilization
48.4%
Of revised budget
Cost Status
+18.3%
+₹395 Cr increase
Remaining
₹1317 Cr
Budget left
Budget Utilization
48.4%Spent
₹1236 Cr
Remaining
₹1317 Cr
Total
₹2553 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2158 Cr
Revised Cost
₹2553 Cr
Increase
+₹395 Cr
Escalation
+18.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/05/2026
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹395 Cr (18.3%) from the original estimate of ₹2158 Cr.
Expenditure stands at ₹1236 Cr, which is 48.4% of the revised project cost.
Remaining budget: ₹1317 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L Behsuma at Km 39.250 Ex. Km 39240 To Bijnor at Km 78.810 Ex. Km 86590 Design Length 39.560 Km of NH-119 Pkg-II is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2158.00 Cr, later revised to ₹2553.12 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L Behsuma at Km 39.250 Ex. Km 39240 To Bijnor at Km 78.810 Ex. Km 86590 Design "?
- 4L Behsuma at Km 39.250 Ex. Km 39240 To Bijnor at Km 78.810 Ex. Km 86590 Design Length 39.560 Km of NH-119 Pkg-II is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹2158 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2158 Cr and has been revised to ₹2553 Cr — a cost overrun of +18.3%. Expenditure to date: ₹1236 Cr (48.4% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L Behsuma at Km 39.250 Ex. Km 39240 To Bijnor at Km 78.810 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618923. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Behsuma at Km 39.250 Ex. Km 39240 To Bijnor at Km 78.810 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.