Roads & HighwaysIPM · Central Project +1.5% overrun#618812

4L Access Controlled Greenfield Section Mancherial Warangal from Puttapaka village at Design Ch. 35.300 Km to Pangidipalle village at Design Ch. 72.350 KmPackage-II

Ministry of Road Transport & HighwaysTelangana
Revised Cost: ₹1145 CrUtilization: 18.5%Overrun: +₹16 Cr

Original Cost

₹1129 Cr

Baseline estimate

+2% overrun

Revised Cost

₹1145 Cr

Latest approved cost

Expenditure

₹212 Cr

Spent to date

Utilization

18.5%

Of revised budget

Escalated

Cost Status

+1.5%

+₹16 Cr increase

Remaining

₹934 Cr

Budget left

Budget Utilization

18.5%
0%25%50%75%100%

Spent

₹212 Cr

Remaining

₹934 Cr

Total

₹1145 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1129 Cr

Revised Cost

₹1145 Cr

Increase

+₹16 Cr

Escalation

+1.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

13/06/2027

Revised Completion

31/12/2027

Completed

Project Details

Project Code618812
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTelangana
Data Month2026-08

Financial Summary

Original Cost₹1129 Cr
Revised Cost₹1145 Cr
Expenditure₹212 Cr
Original End Date13/06/2027
Revised Date31/12/2027

Project Intelligence

Cost has increased by ₹16 Cr (1.5%) from the original estimate of ₹1129 Cr.

Expenditure stands at ₹212 Cr, which is 18.5% of the revised project cost.

Remaining budget: ₹934 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4L Access Controlled Greenfield Section Mancherial Warangal from Puttapaka village at Design Ch. 35.300 Km to Pangidipalle village at Design Ch. 72.350 KmPackage-II is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1129.00 Cr, later revised to ₹1145.41 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4L Access Controlled Greenfield Section Mancherial Warangal from Puttapaka vill"?
4L Access Controlled Greenfield Section Mancherial Warangal from Puttapaka village at Design Ch. 35.300 Km to Pangidipalle village at Design Ch. 72.350 KmPackage-II is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹1129 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1129 Cr and has been revised to ₹1145 Cr — a cost overrun of +1.5%. Expenditure to date: ₹212 Cr (18.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4L Access Controlled Greenfield Section Mancherial Warangal is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618812. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Access Controlled Greenfield Section Mancherial Warangal is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.