4L Access Controlled Greenfield Section Mancherial Warangal from Puttapaka village at Design Ch. 35.300 Km to Pangidipalle village at Design Ch. 72.350 KmPackage-II
Original Cost
₹1129 Cr
Baseline estimate
Revised Cost
₹1145 Cr
Latest approved cost
Expenditure
₹212 Cr
Spent to date
Utilization
18.5%
Of revised budget
Cost Status
+1.5%
+₹16 Cr increase
Remaining
₹934 Cr
Budget left
Budget Utilization
18.5%Spent
₹212 Cr
Remaining
₹934 Cr
Total
₹1145 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1129 Cr
Revised Cost
₹1145 Cr
Increase
+₹16 Cr
Escalation
+1.5%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
13/06/2027
Revised Completion
31/12/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹16 Cr (1.5%) from the original estimate of ₹1129 Cr.
Expenditure stands at ₹212 Cr, which is 18.5% of the revised project cost.
Remaining budget: ₹934 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4L Access Controlled Greenfield Section Mancherial Warangal from Puttapaka village at Design Ch. 35.300 Km to Pangidipalle village at Design Ch. 72.350 KmPackage-II is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1129.00 Cr, later revised to ₹1145.41 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4L Access Controlled Greenfield Section Mancherial Warangal from Puttapaka vill"?
- 4L Access Controlled Greenfield Section Mancherial Warangal from Puttapaka village at Design Ch. 35.300 Km to Pangidipalle village at Design Ch. 72.350 KmPackage-II is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Telangana. Original cost: ₹1129 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1129 Cr and has been revised to ₹1145 Cr — a cost overrun of +1.5%. Expenditure to date: ₹212 Cr (18.5% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4L Access Controlled Greenfield Section Mancherial Warangal is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618812. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4L Access Controlled Greenfield Section Mancherial Warangal is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.