Original Cost
₹1129 Cr
Baseline estimate
Revised Cost
₹1145 Cr
Latest approved cost
Expenditure
₹80 Cr
Spent to date
Utilization
7.0%
Of revised budget
Cost Status
+1.5%
+₹16 Cr increase
Remaining
₹1065 Cr
Budget left
Spent
₹80 Cr
Remaining
₹1065 Cr
Total
₹1145 Cr
Original Cost
₹1129 Cr
Revised Cost
₹1145 Cr
Increase
+₹16 Cr
Escalation
+1.5%
Project Approved
Construction / Implementation
Original End Date
13/06/2027
Revised Completion
31/12/2027
Completed
Cost has increased by ₹16 Cr (1.5%) from the original estimate of ₹1129 Cr.
Expenditure stands at ₹80 Cr, which is 7.0% of the revised project cost.
Remaining budget: ₹1065 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.