Original Cost
₹1143 Cr
Baseline estimate
Revised Cost
₹1141 Cr
Latest approved cost
Expenditure
₹66 Cr
Spent to date
Utilization
5.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1075 Cr
Budget left
Spent
₹66 Cr
Remaining
₹1075 Cr
Total
₹1141 Cr
Project Approved
Construction / Implementation
Original End Date
12/06/2027
Revised Completion
31/05/2028
Completed
Project is within original budget of ₹1143 Cr — no cost escalation recorded.
Expenditure stands at ₹66 Cr, which is 5.8% of the revised project cost.
Remaining budget: ₹1075 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.