Original Cost
₹1105 Cr
Baseline estimate
Revised Cost
₹1098 Cr
Latest approved cost
Expenditure
₹109 Cr
Spent to date
Utilization
9.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹989 Cr
Budget left
Spent
₹109 Cr
Remaining
₹989 Cr
Total
₹1098 Cr
Project Approved
Construction / Implementation
Original End Date
03/07/2027
Revised Completion
03/07/2027
Completed
Project is within original budget of ₹1105 Cr — no cost escalation recorded.
Expenditure stands at ₹109 Cr, which is 9.9% of the revised project cost.
Remaining budget: ₹989 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.