Original Cost
₹826 Cr
Baseline estimate
Revised Cost
₹863 Cr
Latest approved cost
Expenditure
₹103 Cr
Spent to date
Utilization
12.0%
Of revised budget
Cost Status
+4.4%
+₹37 Cr increase
Remaining
₹760 Cr
Budget left
Spent
₹103 Cr
Remaining
₹760 Cr
Total
₹863 Cr
Original Cost
₹826 Cr
Revised Cost
₹863 Cr
Increase
+₹37 Cr
Escalation
+4.4%
Project Approved
Construction / Implementation
Original End Date
26/03/2027
Revised Completion
30/06/2027
Completed
Cost has increased by ₹37 Cr (4.4%) from the original estimate of ₹826 Cr.
Expenditure stands at ₹103 Cr, which is 12.0% of the revised project cost.
Remaining budget: ₹760 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.