Original Cost
₹1501 Cr
Baseline estimate
Revised Cost
₹1815 Cr
Latest approved cost
Expenditure
₹993 Cr
Spent to date
Utilization
54.7%
Of revised budget
Cost Status
+20.9%
+₹314 Cr increase
Remaining
₹822 Cr
Budget left
Spent
₹993 Cr
Remaining
₹822 Cr
Total
₹1815 Cr
Original Cost
₹1501 Cr
Revised Cost
₹1815 Cr
Increase
+₹314 Cr
Escalation
+20.9%
Project Approved
Construction / Implementation
Original End Date
15/02/2025
Revised Completion
31/05/2026
Completed
Cost has increased by ₹314 Cr (20.9%) from the original estimate of ₹1501 Cr.
Expenditure stands at ₹993 Cr, which is 54.7% of the revised project cost.
Remaining budget: ₹822 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.