4 Laning of Talcher to end of Kamakhyanagar Bypass km 8.844 - km 15.725 of NH-149 and km 301.875 - km 335.946 of NH-53 Pkg-I
Original Cost
₹795 Cr
Baseline estimate
Revised Cost
₹811 Cr
Latest approved cost
Expenditure
₹716 Cr
Spent to date
Utilization
88.3%
Of revised budget
Cost Status
+2.0%
+₹16 Cr increase
Remaining
₹95 Cr
Budget left
Budget Utilization
88.3%Spent
₹716 Cr
Remaining
₹95 Cr
Total
₹811 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹795 Cr
Revised Cost
₹811 Cr
Increase
+₹16 Cr
Escalation
+2.0%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/08/2021
Revised Completion
31/10/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹16 Cr (2.0%) from the original estimate of ₹795 Cr.
Expenditure stands at ₹716 Cr, which is 88.3% of the revised project cost.
Remaining budget: ₹95 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4 Laning of Talcher to end of Kamakhyanagar Bypass km 8.844 - km 15.725 of NH-149 and km 301.875 - km 335.946 of NH-53 Pkg-I is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹795.00 Cr, later revised to ₹810.71 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4 Laning of Talcher to end of Kamakhyanagar Bypass km 8.844 - km 15.725 of NH-14"?
- 4 Laning of Talcher to end of Kamakhyanagar Bypass km 8.844 - km 15.725 of NH-149 and km 301.875 - km 335.946 of NH-53 Pkg-I is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹795 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹795 Cr and has been revised to ₹811 Cr — a cost overrun of +2%. Expenditure to date: ₹716 Cr (88.3% of revised cost). Data as of 2026-07.
- QWhich ministry is responsible for this project?
- 4 Laning of Talcher to end of Kamakhyanagar Bypass km 8.844 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619157. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4 Laning of Talcher to end of Kamakhyanagar Bypass km 8.844 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.