Original Cost
₹795 Cr
Baseline estimate
Revised Cost
₹811 Cr
Latest approved cost
Expenditure
₹403 Cr
Spent to date
Utilization
49.7%
Of revised budget
Cost Status
+2.0%
+₹16 Cr increase
Remaining
₹407 Cr
Budget left
Spent
₹403 Cr
Remaining
₹407 Cr
Total
₹811 Cr
Original Cost
₹795 Cr
Revised Cost
₹811 Cr
Increase
+₹16 Cr
Escalation
+2.0%
Project Approved
Construction / Implementation
Original End Date
19/08/2021
Revised Completion
31/10/2026
Completed
Cost has increased by ₹16 Cr (2.0%) from the original estimate of ₹795 Cr.
Expenditure stands at ₹403 Cr, which is 49.7% of the revised project cost.
Remaining budget: ₹407 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.