Roads & HighwaysIPM · Central Project +2.0% overrun#619157

4 Laning of Talcher to end of Kamakhyanagar Bypass km 8.844 - km 15.725 of NH-149 and km 301.875 - km 335.946 of NH-53 Pkg-I

Ministry of Road Transport & HighwaysOdisha
Revised Cost: ₹811 CrUtilization: 88.3%Overrun: +₹16 Cr

Original Cost

₹795 Cr

Baseline estimate

+2% overrun

Revised Cost

₹811 Cr

Latest approved cost

Expenditure

₹716 Cr

Spent to date

Utilization

88.3%

Of revised budget

Escalated

Cost Status

+2.0%

+₹16 Cr increase

Remaining

₹95 Cr

Budget left

Budget Utilization

88.3%
0%25%50%75%100%

Spent

₹716 Cr

Remaining

₹95 Cr

Total

₹811 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹795 Cr

Revised Cost

₹811 Cr

Increase

+₹16 Cr

Escalation

+2.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

19/08/2021

Revised Completion

31/10/2026

Completed

Project Details

Project Code619157
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateOdisha
Data Month2026-07

Financial Summary

Original Cost₹795 Cr
Revised Cost₹811 Cr
Expenditure₹716 Cr
Original End Date19/08/2021
Revised Date31/10/2026

Project Intelligence

Cost has increased by ₹16 Cr (2.0%) from the original estimate of ₹795 Cr.

Expenditure stands at ₹716 Cr, which is 88.3% of the revised project cost.

Remaining budget: ₹95 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4 Laning of Talcher to end of Kamakhyanagar Bypass km 8.844 - km 15.725 of NH-149 and km 301.875 - km 335.946 of NH-53 Pkg-I is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹795.00 Cr, later revised to ₹810.71 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4 Laning of Talcher to end of Kamakhyanagar Bypass km 8.844 - km 15.725 of NH-14"?
4 Laning of Talcher to end of Kamakhyanagar Bypass km 8.844 - km 15.725 of NH-149 and km 301.875 - km 335.946 of NH-53 Pkg-I is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹795 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹795 Cr and has been revised to ₹811 Cr — a cost overrun of +2%. Expenditure to date: ₹716 Cr (88.3% of revised cost). Data as of 2026-07.
QWhich ministry is responsible for this project?
4 Laning of Talcher to end of Kamakhyanagar Bypass km 8.844 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619157. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4 Laning of Talcher to end of Kamakhyanagar Bypass km 8.844 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.