4- Laning of Mohari to Satai Ghat section NH-934 from Km 50300 to Km 89875 Total length 39.575 km Package-2 in the State of Madhya Pradesh on EPC Mode
Original Cost
₹711 Cr
Baseline estimate
Revised Cost
₹539 Cr
Latest approved cost
Expenditure
₹533 Cr
Spent to date
Utilization
98.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹6 Cr
Budget left
Budget Utilization
98.9%Spent
₹533 Cr
Remaining
₹6 Cr
Total
₹539 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
23/08/2026
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹711 Cr — no cost escalation recorded.
Expenditure stands at ₹533 Cr, which is 98.9% of the revised project cost.
Remaining budget: ₹6 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4- Laning of Mohari to Satai Ghat section NH-934 from Km 50300 to Km 89875 Total length 39.575 km Package-2 in the State of Madhya Pradesh on EPC Mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹711.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4- Laning of Mohari to Satai Ghat section NH-934 from Km 50300 to Km 89875 Total"?
- 4- Laning of Mohari to Satai Ghat section NH-934 from Km 50300 to Km 89875 Total length 39.575 km Package-2 in the State of Madhya Pradesh on EPC Mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹711 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹711 Cr and has been revised to ₹539 Cr — a cost overrun of -24.2%. Expenditure to date: ₹533 Cr (98.9% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4- Laning of Mohari to Satai Ghat section NH-934 from Km 503 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618666. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4- Laning of Mohari to Satai Ghat section NH-934 from Km 503 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.