Original Cost
₹711 Cr
Baseline estimate
Revised Cost
₹539 Cr
Latest approved cost
Expenditure
₹467 Cr
Spent to date
Utilization
86.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹72 Cr
Budget left
Spent
₹467 Cr
Remaining
₹72 Cr
Total
₹539 Cr
Project Approved
Construction / Implementation
Original End Date
27/08/2026
Revised Completion
31/08/2026
Completed
Project is within original budget of ₹711 Cr — no cost escalation recorded.
Expenditure stands at ₹467 Cr, which is 86.7% of the revised project cost.
Remaining budget: ₹72 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.