4-Laning of Jamugurihat to end of Biswanath Chariali By-Pass from Km 182.000 to Km 208.000 of NH-52 on EPC mode in state of Assam under SARDP-NE

Ministry of Road Transport & HighwaysAssam
Revised Cost: ₹599 CrUtilization: 72.4%

Original Cost

₹599 Cr

Baseline estimate

On budget

Revised Cost

₹599 Cr

Latest approved cost

Expenditure

₹434 Cr

Spent to date

Utilization

72.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹165 Cr

Budget left

Budget Utilization

72.4%
0%25%50%75%100%

Spent

₹434 Cr

Remaining

₹165 Cr

Total

₹599 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

19/06/2019

Revised Completion

30/07/2025

Completed

Project Details

Project Code618436
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAssam
Data Month2026-08

Financial Summary

Original Cost₹599 Cr
Revised Cost₹599 Cr
Expenditure₹434 Cr
Original End Date19/06/2019
Revised Date30/07/2025

Project Intelligence

Project is within original budget of ₹599 Cr — no cost escalation recorded.

Expenditure stands at ₹434 Cr, which is 72.4% of the revised project cost.

Remaining budget: ₹165 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

4-Laning of Jamugurihat to end of Biswanath Chariali By-Pass from Km 182.000 to Km 208.000 of NH-52 on EPC mode in state of Assam under SARDP-NE is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹599.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "4-Laning of Jamugurihat to end of Biswanath Chariali By-Pass from Km 182.000 to "?
4-Laning of Jamugurihat to end of Biswanath Chariali By-Pass from Km 182.000 to Km 208.000 of NH-52 on EPC mode in state of Assam under SARDP-NE is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹599 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹599 Cr has not been significantly revised. Expenditure: ₹434 Cr (72.4% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
4-Laning of Jamugurihat to end of Biswanath Chariali By-Pass is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618436. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4-Laning of Jamugurihat to end of Biswanath Chariali By-Pass is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.