4 Lane with PS from Des. Ch 182.300 to Des. Ch. 228.500 of Belgaum-Hungund-Raichur Section of NH 748 A Package-5
Original Cost
₹1142 Cr
Baseline estimate
Revised Cost
₹869 Cr
Latest approved cost
Expenditure
₹271 Cr
Spent to date
Utilization
31.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹598 Cr
Budget left
Budget Utilization
31.2%Spent
₹271 Cr
Remaining
₹598 Cr
Total
₹869 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
20/11/2026
Revised Completion
31/08/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1142 Cr — no cost escalation recorded.
Expenditure stands at ₹271 Cr, which is 31.2% of the revised project cost.
Remaining budget: ₹598 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
4 Lane with PS from Des. Ch 182.300 to Des. Ch. 228.500 of Belgaum-Hungund-Raichur Section of NH 748 A Package-5 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1142.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "4 Lane with PS from Des. Ch 182.300 to Des. Ch. 228.500 of Belgaum-Hungund-Raich"?
- 4 Lane with PS from Des. Ch 182.300 to Des. Ch. 228.500 of Belgaum-Hungund-Raichur Section of NH 748 A Package-5 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹1142 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1142 Cr and has been revised to ₹869 Cr — a cost overrun of -23.9%. Expenditure to date: ₹271 Cr (31.2% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 4 Lane with PS from Des. Ch 182.300 to Des. Ch. 228.500 of B is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619106. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 4 Lane with PS from Des. Ch 182.300 to Des. Ch. 228.500 of B is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.