Original Cost
₹1000 Cr
Baseline estimate
Revised Cost
₹1000 Cr
Latest approved cost
Expenditure
₹417 Cr
Spent to date
Utilization
41.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹583 Cr
Budget left
Spent
₹417 Cr
Remaining
₹583 Cr
Total
₹1000 Cr
Project Approved
Construction / Implementation
Original End Date
11/06/2026
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹1000 Cr — no cost escalation recorded.
Expenditure stands at ₹417 Cr, which is 41.7% of the revised project cost.
Remaining budget: ₹583 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.