Original Cost
₹1265 Cr
Baseline estimate
Revised Cost
₹1265 Cr
Latest approved cost
Expenditure
₹471 Cr
Spent to date
Utilization
37.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹794 Cr
Budget left
Spent
₹471 Cr
Remaining
₹794 Cr
Total
₹1265 Cr
Project Approved
Construction / Implementation
Original End Date
18/06/2026
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹1265 Cr — no cost escalation recorded.
Expenditure stands at ₹471 Cr, which is 37.2% of the revised project cost.
Remaining budget: ₹794 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.