Original Cost
₹706 Cr
Baseline estimate
Revised Cost
₹753 Cr
Latest approved cost
Expenditure
₹516 Cr
Spent to date
Utilization
68.5%
Of revised budget
Cost Status
+6.6%
+₹47 Cr increase
Remaining
₹237 Cr
Budget left
Spent
₹516 Cr
Remaining
₹237 Cr
Total
₹753 Cr
Original Cost
₹706 Cr
Revised Cost
₹753 Cr
Increase
+₹47 Cr
Escalation
+6.6%
Project Approved
Construction / Implementation
Original End Date
06/01/2024
Revised Completion
10/06/2025
Completed
Cost has increased by ₹47 Cr (6.6%) from the original estimate of ₹706 Cr.
Expenditure stands at ₹516 Cr, which is 68.5% of the revised project cost.
Remaining budget: ₹237 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.