2L PS of JH / WB Border km. 70.524 - Purulia km.84.400 & Purulia km. 94.30 - Chandil Junction with NH-33 km. 153.705 of Old NH-32
Original Cost
₹1652 Cr
Baseline estimate
Revised Cost
₹1772 Cr
Latest approved cost
Expenditure
₹1652 Cr
Spent to date
Utilization
93.3%
Of revised budget
Cost Status
+7.3%
+₹120 Cr increase
Remaining
₹119 Cr
Budget left
Budget Utilization
93.3%Spent
₹1652 Cr
Remaining
₹119 Cr
Total
₹1772 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1652 Cr
Revised Cost
₹1772 Cr
Increase
+₹120 Cr
Escalation
+7.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
06/08/2022
Revised Completion
31/10/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹120 Cr (7.3%) from the original estimate of ₹1652 Cr.
Expenditure stands at ₹1652 Cr, which is 93.3% of the revised project cost.
Remaining budget: ₹119 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
2L PS of JH / WB Border km. 70.524 - Purulia km.84.400 & Purulia km. 94.30 - Chandil Junction with NH-33 km. 153.705 of Old NH-32 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1652.00 Cr, later revised to ₹1771.88 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "2L PS of JH / WB Border km. 70.524 - Purulia km.84.400 & Purulia km. 94.30 - Cha"?
- 2L PS of JH / WB Border km. 70.524 - Purulia km.84.400 & Purulia km. 94.30 - Chandil Junction with NH-33 km. 153.705 of Old NH-32 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: West Bengal. Original cost: ₹1652 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1652 Cr and has been revised to ₹1772 Cr — a cost overrun of +7.3%. Expenditure to date: ₹1652 Cr (93.3% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 2L PS of JH / WB Border km. 70.524 - Purulia km.84.400 & Pur is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618909. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 2L PS of JH / WB Border km. 70.524 - Purulia km.84.400 & Pur is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.