Muzaffarpur·Muzaffarpur·Bihar
Admin Approval
₹4387 L
Agreement Amount
₹3519805.58 Cr
Commencement
07 Feb 2024
Scheduled Completion
06 Feb 2026
Foundation (Pile)- 54/78 Nos. Sub Structure-07/11 Nos. Deck slab -0/10 Nos. RE Wall- 0/325 Mtr (Panel Casting is in Progress) Girder casting- 15/36 Nos. Agency has been debarred for slow progress on dated 14.02.2026