Saran Works·Saran·Bihar
Admin Approval
₹5937 L
Agreement Amount
₹48.07 Cr
Commencement
04 Nov 2023
Scheduled Completion
03 Nov 2025
Pile 90/90, Pile cap 11/11, Sub structure Pier 11/11, Pier head 11/11, Girder casting 21/21, Deck slab 7/10, Superstructure work in progress. Foundation and Substructure work completed. Rs 206.97 Lakh paid to DLAO on 06.04.26 for LA