Saran Works·Saran·Bihar
Admin Approval
₹41131 L
Agreement Amount
₹370.61 Cr
Commencement
07 Jun 2018
Scheduled Completion
06 Jun 2022
Piles 1453/1534 Nos. Pile Cap120/143 Nos. Pier Shaft (Deck-1) 66/100 Nos. Pier Shaft (Deck-2) 101/138, Portal Beam (Deck-1) 64/100, Portal Beam (Deck-2)95/138 Girder Erection 140/236 Deck slab 125/236 RS Wall Panel Casting-2215/3100 Nos. Total 2198M Remarks for LA: LA- 1. Unsurveyed Land- Status Quo has been removed by Hon'ble Patna H.C. on dt. 17.02.25. Work restarted. 2. Surveyed Land- Cheque No.752625 of Rs. 20.58 Cr. has been paid to DLAO, Saran Chhapra