Construction of New DVOR Building at Khajuraho Airport. SH Electrical Works.
Tender Description
Construction of New DVOR Building at Khajuraho Airport. SH Electrical Works.
Tender Specifications & Timeline
14 FieldsAward of Contract (AOC) Details
Awardee / Contractor
M/S SANDEEP KUMAR TIWARI
Award Date: 01-Aug-2025
Completion Period: 120 Days
Contract Financials & Scope
INR 5,777,850
Work has been Awarded
Contract Award Info Updated 01-Aug-2025 05:47 PM by Ravi Singh
Total Bidders
7
Winning Bid (L1)
₹57.78 L
Estimated Value
₹72.45 L
Margin vs Estimate
-20.25%
L1 to L2 Spread
+19.30%
Completion Period
120 days
AOC Award Date
01-Aug-2025
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | M/S SANDEEP KUMAR TIWARI#848562 | ₹57.78 L | 0.0% (L1) | -20.25% | Accepted-AOC |
| L2 | DOSHI ELECTRIC ENGG. CO.#848134 | ₹68.93 L | +19.30% | Rejected-Fin | Rejected-Finance |
| L3 | Manish Electricals#848525 | ₹73.99 L | +28.05% | Rejected-Fin | Rejected-Finance |
| L4 | Yash Energy Pvt. Ltd#848793 | ₹80.53 L | +39.38% | Rejected-Fin | Rejected-Finance |
| DQ | Awasthi Electric Works#848785 | — | — | Rejected-Tech | Rejected-Technical |
| DQ | — | — | Rejected-Tech | Rejected-Technical | |
| DQ | Shiva Enterprises#848665 | — | — | Rejected-Tech | Rejected-Technical |
This airports tender covers construction of New DVOR Building at Khajuraho Airport. SH Electrical Works., issued by Airports Authority of India under reference AAI/Engg(E)/KHJ/NIT-02/2025-26. The estimated contract value is ₹0.72 Cr, and The tender is currently Expired.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in Khajuraho Airport. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents
Download official tender documents, technical specifications, schedules, and BOQ files
techsummary_263483.pdf
BOQ Comparative Chart
finsummary_263483.pdf
DVORWorkOrderAgency.pdf
Not eligible due to not fulfilling requirement of minimum annual value of Engg. Electrical construction works as per NIT
L2 Agency
Not eligible due to Non submission of document for annul value of general construction work and Engg. Electrical construction works
L3 Agency
Work has been Awarded
Not eligible due to non submission of documents as per NIT criteria
L4 Agency
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
Awasthi Electric Works #848785 | 08-May-2025 05:35 PM | Rejected-Technical Updated: 20-May-2025 02:29 PM | — | — | Not eligible due to not fulfilling requirement of minimum annual value of Engg. Electrical construction works as per NIT |
DOSHI ELECTRIC ENGG. CO. #848134 | 08-May-2025 12:15 PM | Rejected-Finance Updated: 10-Jun-2025 12:58 PM | 68,92,775.00 | L2 | L2 Agency |
JCC ENGINEERS PRIVATE LIMITED #848353 | 08-May-2025 11:54 AM | Rejected-Technical Updated: 20-May-2025 02:29 PM | — | — | Not eligible due to Non submission of document for annul value of general construction work and Engg. Electrical construction works |
Manish Electricals #848525 | 08-May-2025 12:38 PM | Rejected-Finance Updated: 10-Jun-2025 12:58 PM | 73,98,660.00 | L3 | L3 Agency |
M/S SANDEEP KUMAR TIWARI #848562 | 08-May-2025 05:05 PM | Accepted-AOC Updated: 01-Aug-2025 05:48 PM | 57,77,850.00 | L1 | Work has been Awarded |
Shiva Enterprises #848665 | 08-May-2025 04:11 PM | Rejected-Technical Updated: 20-May-2025 02:29 PM | — | — | Not eligible due to non submission of documents as per NIT criteria |
Yash Energy Pvt. Ltd #848793 | 08-May-2025 05:59 PM | Rejected-Finance Updated: 10-Jun-2025 12:58 PM | 80,53,278.00 | L4 | L4 Agency |
Bid Evaluation Details & Logs
technical bid opening
Date: 14-May-2025 11:44 AM
Officer: Ravi Singh
All bidders have been admitted
technical evaluation
Date: 20-May-2025 02:29 PM
Officer: Ravi Singh
finance bid opening
Date: 21-May-2025 02:43 PM
Officer: Ravi Singh
4 Nos. bids are opened
finance evaluation
Date: 10-Jun-2025 12:58 PM
Officer: Ravi Singh
About This Procurement Notice
This central government tender was issued by Airports Authority of India. The estimated contract value is ₹72.45 L. Bids must be submitted by 08-May-2025 06:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Construction of New DVOR Building at Khajuraho Airport. SH Electrical Works."?
- The current status of this tender is "Expired". The submission deadline is 08-May-2025 06:00 PM. This information is sourced from official government procurement portals.
- QWho issued this Bihar government tender?
- This tender was issued by Airports Authority of India. The reference number is AAI/Engg(E)/KHJ/NIT-02/2025-26. It is a central government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹72.45 L. This is the approximate contract value as disclosed in the official tender document.