Balance Terminal Works for Bongaigaon Refinery and Noonmati Refinery Spurlines Under Barauni Guwahati Pipeline Project
Tender Description
BALANCE TERMINAL WORKS FOR BONGAIGAON REFINERY AND NOONMATI REFINERY SPURLINES UNDER BARAUNI GUWAHATI PIPELINE PROJECT
Tender Specifications & Timeline
14 FieldsAward of Contract (AOC) Details
Awardee / Contractor
NOPS INFRASTRUCTURE PVT. LTD.
Award Date: 18-May-2024
Completion Period: 180 Days
Contract Financials & Scope
INR 73,317,876
Contract Award Info Updated 18-May-2024 10:23 AM by RAKESH SHARMA
Total Bidders
2
Winning Bid (L1)
₹8.65 Cr
Estimated Value
—
Margin vs Estimate
—
L1 to L2 Spread
+51.95%
Completion Period
180 days
AOC Award Date
18-May-2024
| Rank | Bidder / Contractor | Quoted Bid | Gap vs L1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | ₹8.65 Cr | 0.0% (L1) | — | Accepted-AOC | |
| L2 | ₹13.15 Cr | +51.95% | Rejected | Rejected-AOC |
This oil & gas tender covers balance Terminal Works for Bongaigaon Refinery and Noonmati Refinery Spurlines Under Barauni Guwahati Pipeline Project, issued by Gail India Limited under reference 05/51/23U2/GAIL/001(i)-13. This work is part of the development of Noida Water Supply — government tender titles use official department terminology rather than the common name. The tender is currently Expired.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in Noida. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents
Download official tender documents, technical specifications, schedules, and BOQ files
techsummary_166228.pdf
BOQ Comparative Chart
finsummary_166228.pdf
FOANopsInfra.pdf
Awarded, L1 Bidder
Not Awarded
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
NOPS INFRASTRUCTURE PVT. LTD. #550951 | 08-May-2023 12:10 PM | Accepted-AOC Updated: 18-May-2024 10:28 AM | 8,65,15,093.68 | L1 | Awarded, L1 Bidder |
oval projects engineering pvt ltd #551442 | 08-May-2023 01:45 PM | Rejected-AOC Updated: 18-May-2024 10:28 AM | 13,14,62,974.00 | L2 | Not Awarded |
Bid Evaluation Details & Logs
technical bid opening
Date: 09-May-2023 03:07 PM
Officer: RAKESH SHARMA
Technical Bid Opening
technical evaluation
Date: 08-Jun-2023 11:11 AM
Officer: RAKESH SHARMA
finance bid opening
Date: 08-Jun-2023 04:12 PM
Officer: RAKESH SHARMA
Price Bid Opening
finance evaluation
Date: 18-May-2024 10:19 AM
Officer: RAKESH SHARMA
About This Procurement Notice
This central government tender was issued by Gail India Limited. Bids must be submitted by 08-May-2023 03:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Balance Terminal Works for Bongaigaon Refinery and Noonmati Refinery Spurlines U"?
- The current status of this tender is "Expired". The submission deadline is 08-May-2023 03:00 PM. This information is sourced from official government procurement portals.
- QWho issued this Bihar government tender?
- This tender was issued by Gail India Limited. The reference number is 05/51/23U2/GAIL/001(i)-13. It is a central government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value has not been disclosed for this procurement notice. Please refer to the official tender documents for detailed specifications.
- QIs this the Noida Water Supply tender?
- Yes — "Balance Terminal Works for Bongaigaon Refinery and Noonmati Refinery Spurlines Under Barauni Guwahati Pipeline Project" is the official government tender title covering Noida Water Supply development works. Government tender titles for this sector use official department terminology rather than the site's common name.