Construction of DVOR building at CSI Airport Mumbai
Tender Specifications & Timeline
13 FieldsAward of Contract (AOC) Details
Awardee / Contractor
Sree Lalitha Constructions
Award Date: 22-Feb-2022
Completion Period: 151 Days
Contract Financials & Scope
INR 7,267,384
Work awarded on 15.02.2022. The above tendered amount is exclusive of GST
Contract Award Info Updated 22-Feb-2022 03:21 PM by Jaipal Badge
Total Bidders
10
Winning Bid (H1)
₹72.67 L
Estimated Value
₹97.00 L
Margin vs Estimate
-25.08%
Completion Period
151 days
AOC Award Date
22-Feb-2022
| Rank | Bidder / Contractor | Quoted Bid | Gap vs H1 | vs Estimate | Status |
|---|---|---|---|---|---|
| L1 | Sree Lalitha Constructions#361608 | ₹72.67 L | 0.0% (H1) | -25.08% | Accepted-AOC |
| L2 | M K CONSTRUCTION#360373 | ₹78.96 L | +8.65% | Rejected-Fin | Rejected-Finance |
| L3 | ₹81.51 L | +12.15% | Rejected-Fin | Rejected-Finance | |
| L4 | ₹82.65 L | +13.73% | Rejected-Fin | Rejected-Finance | |
| L5 | ₹90.84 L | +25.00% | Rejected-Fin | Rejected-Finance | |
| L6 | ₹93.77 L | +29.02% | Rejected-Fin | Rejected-Finance | |
| L7 | K N RAI#357935 | ₹94.91 L | +30.59% | Rejected-Fin | Rejected-Finance |
| L8 | arcoma#355939 | ₹98.64 L | +35.73% | Rejected-Fin | Rejected-Finance |
| DQ | BALVIR SINGH AND SONS#356766 | — | — | Rejected-Tech | Rejected-Technical |
| DQ | D B Infratech#358768 | — | — | Rejected-Tech | Rejected-Technical |
This airports tender covers construction of DVOR building at CSI Airport Mumbai, issued by Airports Authority of India under reference AAI/WR/MUM/ATS/E-C/21-22/143. The estimated contract value is ₹0.97 Cr, and The tender is currently Expired.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in ATS Complex. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents
Download official tender documents, technical specifications, schedules, and BOQ files
techsummary_105586.pdf
finance_105586.pdf
BOQ Comparative Chart
finsummary_105586.pdf
DVORWorkOrder.pdf
Highest Bid
Not replied shortfall
Highest Bid
Highest Bid
Not replied shortfall
Highest Bid
Highest Bid
Highest Bid
Highest Bid
L1 bidder
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
arcoma #355939 | 16-Dec-2021 12:02 PM | Rejected-Finance Updated: 22-Feb-2022 03:04 PM | 98,64,279.00 | L8 | Highest Bid |
BALVIR SINGH AND SONS #356766 | 16-Dec-2021 07:40 AM | Rejected-Technical Updated: 18-Jan-2022 12:02 PM | — | — | Not replied shortfall |
CIS GLOBAL INFRATECH PRIVATE LIMITED #361866 | 16-Dec-2021 04:06 PM | Rejected-Finance Updated: 22-Feb-2022 03:04 PM | 90,83,999.00 | L5 | Highest Bid |
Classion Projects (I) Pvt. Ltd. #361756 | 16-Dec-2021 02:45 PM | Rejected-Finance Updated: 22-Feb-2022 03:04 PM | 93,76,580.00 | L6 | Highest Bid |
D B Infratech #358768 | 16-Dec-2021 03:19 PM | Rejected-Technical Updated: 18-Jan-2022 12:02 PM | — | — | Not replied shortfall |
GREEN INDIA CONSTRUCTION COMPANY #360787 | 16-Dec-2021 01:27 AM | Rejected-Finance Updated: 22-Feb-2022 03:04 PM | 81,50,697.00 | L3 | Highest Bid |
K N RAI #357935 | 16-Dec-2021 03:20 PM | Rejected-Finance Updated: 22-Feb-2022 03:04 PM | 94,90,599.00 | L7 | Highest Bid |
M K CONSTRUCTION #360373 | 14-Dec-2021 09:04 AM | Rejected-Finance Updated: 22-Feb-2022 03:04 PM | 78,96,318.00 | L2 | Highest Bid |
S. N. ELECTRIC & MAINTENANCE PRIVATE LIMITED #361828 | 16-Dec-2021 02:59 PM | Rejected-Finance Updated: 22-Feb-2022 03:04 PM | 82,65,434.82 | L4 | Highest Bid |
Sree Lalitha Constructions #361608 | 16-Dec-2021 04:51 PM | Accepted-AOC Updated: 22-Feb-2022 03:21 PM | 72,67,384.00 | L1 | L1 bidder |
Bid Evaluation Details & Logs
technical bid opening
Date: 07-Jan-2022 12:51 PM
Officer: Jaipal Badge
All bidder are accepted.
technical evaluation
Date: 18-Jan-2022 12:01 PM
Officer: Jaipal Badge
finance bid opening
Date: 18-Jan-2022 01:11 PM
Officer: Jaipal Badge
All bidder accepted
finance evaluation
Date: 22-Feb-2022 03:03 PM
Officer: Jaipal Badge
About This Procurement Notice
This central government tender was issued by Airports Authority of India. The estimated contract value is ₹97.00 L. Bids must be submitted by 16-Dec-2021 06:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- QWhat is the status of the tender "Construction of DVOR building at CSI Airport Mumbai"?
- The current status of this tender is "Expired". The submission deadline is 16-Dec-2021 06:00 PM. This information is sourced from official government procurement portals.
- QWho issued this Bihar government tender?
- This tender was issued by Airports Authority of India. The reference number is AAI/WR/MUM/ATS/E-C/21-22/143. It is a central government procurement notice.
- QWhat is the estimated value of this tender?
- The estimated tender value is ₹97.00 L. This is the approximate contract value as disclosed in the official tender document.