Renovation work at EXECUTIVE DIRECTOR/Civil/P-II Office at Malviya Nagar, New Delhi
Tender Description
Renovation work at EXECUTIVE DIRECTOR/Civil/P-II DMRC Office at Malviya Nagar, New Delhi.
Tender Details
Financial & Timeline
Award of Contract (AOC) Details
Awardee / Contractor
TSN Infrastructure Pvt. Ltd.
Award Date: 10-Jul-2020
Completion Period: 75 Days
Contract Financials & Scope
INR 8,192,483
Contract -Renovation Work at Executive Director/Civil/P-II Office at Malviya Nagar, New Delhi, is awarded to G.S. Engineers And Contractors. Please Refer Uploaded AOC documents for Details.
Contract Award Info Updated 10-Jul-2020 03:13 PM by Siddharth Kashyap
This metro rail tender covers renovation work at EXECUTIVE DIRECTOR/Civil/P-II Office at Malviya Nagar, New Delhi, issued by Delhi Metro Rail Corporation Limited under reference EXECUTIVE DIRECTOR/CIVIL/P-II - Office Renovation. The estimated contract value is ₹0.82 Cr, and The tender is currently Expired.
This procurement is part of ongoing efforts by central government agencies and public sector undertakings to maintain and upgrade public infrastructure and services in ED/Civil/P-II Office, Malviya Nagar, New Delhi. Vendors interested in similar opportunities can browse other tenders from the same issuing organisation below.
Tender Documents & Downloads
techsummary_587801.pdf
Key: 2020_DMRC_560175_1/techsummary_587801.pdf
finsummary_587801.pdf
Key: 2020_DMRC_560175_1/finsummary_587801.pdf
AOC.pdf
Key: 2020_DMRC_560175_1/AOC.pdf
Submitted Bids & Bidder Details
Minimum Annual Average turnover of last five years from Construction works criteria is not fufilled
Rate quoted is higher than the lowest bidder and not accepted by competent authority.
Rate quoted is higher than the lowest bidder and not accepted by competent authority.
Rate quoted is higher than the lowest bidder and not accepted by competent authority.
Lowest Bidders and Approved by Competent Authority
Rate quoted is higher than the lowest bidder and not accepted by competent authority.
Rate quoted is higher than the lowest bidder and not accepted by competent authority.
Minimum Annual Average turnover of last five years from Construction works criteria is not fufilled
Rate quoted is higher than the lowest bidder and not accepted by competent authority.
| Bidder | Submitted On | Status | Fin. Value | Rank | Remarks / Logs |
|---|---|---|---|---|---|
AIDHI PROJECTS PVT LTD #1994392 | 11-Jun-2020 09:31 AM | Rejected-Technical Updated: 01-Jul-2020 07:06 PM | — | — | Minimum Annual Average turnover of last five years from Construction works criteria is not fufilled |
BHAVAN ENTERPRISES #1994224 | 11-Jun-2020 12:28 PM | Rejected-AOC Updated: 10-Jul-2020 03:13 PM | 91,92,411.03 | L-7 | Rate quoted is higher than the lowest bidder and not accepted by competent authority. |
BIT INFRATECH #1994694 | 11-Jun-2020 01:55 PM | Rejected-AOC Updated: 10-Jul-2020 03:13 PM | 72,02,011.98 | L-4 | Rate quoted is higher than the lowest bidder and not accepted by competent authority. |
CONSTRUCTIVE CONSTRUCTION #1994622 | 11-Jun-2020 02:27 PM | Rejected-AOC Updated: 10-Jul-2020 03:13 PM | 73,09,666.75 | L-5 | Rate quoted is higher than the lowest bidder and not accepted by competent authority. |
G S Engineers And Contractors #1994269 | 11-Jun-2020 01:43 PM | Accepted-AOC Updated: 10-Jul-2020 03:13 PM | 67,99,761.05 | L-1 | Lowest Bidders and Approved by Competent Authority |
MAA VAISHNO CONSTRUCTIONS #1994249 | 11-Jun-2020 11:01 AM | Rejected-AOC Updated: 10-Jul-2020 03:13 PM | 71,13,490.90 | L-3 | Rate quoted is higher than the lowest bidder and not accepted by competent authority. |
MODTECH #1994727 | 11-Jun-2020 12:52 PM | Rejected-AOC Updated: 10-Jul-2020 03:13 PM | 70,41,251.58 | L-2 | Rate quoted is higher than the lowest bidder and not accepted by competent authority. |
NITCON CONSTRUCTION #1992891 | 10-Jun-2020 04:22 PM | Rejected-Technical Updated: 01-Jul-2020 07:06 PM | — | — | Minimum Annual Average turnover of last five years from Construction works criteria is not fufilled |
TSN Infrastructure Pvt. Ltd. #1990867 | 11-Jun-2020 01:02 PM | Rejected-AOC Updated: 10-Jul-2020 03:13 PM | 80,97,398.15 | L-6 | Rate quoted is higher than the lowest bidder and not accepted by competent authority. |
Bid Evaluation Details & Logs
technical bid opening
Date: 12-Jun-2020 06:24 PM
Officer: Siddharth Kashyap
Tender has been opened successfully. Total 9 (nine) bids have been received. Now, technical evaluation will start and final acceptance/rejection will be intimated.
technical evaluation
Date: 01-Jul-2020 07:07 PM
Officer: Siddharth Kashyap
finance bid opening
Date: 02-Jul-2020 12:33 PM
Officer: Mohit Ghune
Seven bids have been received and found in order.
finance evaluation
Date: 06-Jul-2020 05:01 PM
Officer: Siddharth Kashyap
About This Procurement Notice
This central government tender was issued by Delhi Metro Rail Corporation Limited. The estimated contract value is ₹81.92 L. Bids must be submitted by 11-Jun-2020 03:00 PM.
BiharInfraTales aggregates procurement notices from Bihar eProcurement, GeM portal, and central government tender portals. Data is refreshed every 30 minutes. Always verify details on the official portal before submitting a bid.
Frequently Asked Questions
- What is the status of the tender "Renovation work at EXECUTIVE DIRECTOR/Civil/P-II Office at Malviya Nagar, New De"?
- The current status of this tender is "Expired". The submission deadline is 11-Jun-2020 03:00 PM. This information is sourced from official government procurement portals.
- Who issued this Bihar government tender?
- This tender was issued by Delhi Metro Rail Corporation Limited. The reference number is EXECUTIVE DIRECTOR/CIVIL/P-II - Office Renovation. It is a central government procurement notice.
- What is the estimated value of this tender?
- The estimated tender value is ₹81.92 L. This is the approximate contract value as disclosed in the official tender document.