MDRRCD BiharOngoning

Widening and Strengthening work of Ekma-Dumaigarh Road (Total Length- 11.75 Km) under Road Division, Chapra for the year 2024-25

#948
Road Division Chapra.
Saran Road Circle Hajipur.
Bihar RCD PMIS — Road Project◐ Ongoning
Agreement₹24.87 Cr
Length11.75 km
Start28-07-2025
Completion27-10-2026
MDR · North Wing
Road Division Chapra.
J. K. Engicon Pvt Ltd.

Project Details

6 Fields
Project No.
948
Wing
North Wing
Division
Road Division Chapra.
Circle
Saran Road Circle Hajipur.
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹24.87 Cr
Sanctioned Length
11.75 km
Contractor
J. K. Engicon Pvt Ltd.
AA Date
05-02-2025
Start Date
28-07-2025
Expected Completion
27-10-2026

Widening and Strengthening work of Ekma-Dumaigarh Road (Total Length- 11.75 Km) under Road Division, Chapra for the year 2024-25 is a Bihar Road Construction Department (RCD) project under Road Division Chapra., classified as a MDR. The agreement amount for this project is ₹24.87 Cr, and the current status is Ongoning.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Section 19 has been completed by DLAO Saran. 11 Nos HP culvert completed and 1 nos hp culvert work in progress. 2 nos box culvert deck slab work is complete. section 11 completed.Drain Work is in progress

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Widening and Strengthening work of Ekma-Dumaigarh Road (Total Length- 11.75 Km) "?
Status: Ongoning. This MDR project under Road Division Chapra. (Saran Road Circle Hajipur.) covers 11.75 km of road work. Expected completion: 27-10-2026.
QWho is the contractor for RCD project 948?
The contractor for this project is J. K. Engicon Pvt Ltd.. Project number: 948. Division: Road Division Chapra.. Administrative approval date: 05-02-2025.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Widening and Strengthening work of Ekma-Dumaigarh Road (Tota" is ₹24.87 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Chapra..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 948 "Widening and Strengthening work of Ekma-Dumaigarh Road (Tota" is one of thousands of road improvement and construction works tracked by BiharInfraTales.