Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /RCD PMIS
  3. /Widening and Strengthening work of Ekma-Masrakh Ro
MDRRCD BiharOngoning

Widening and Strengthening work of Ekma-Masrakh Road from km 0.00 to 31.60 under Road Division, Chapra for the year 2024-25

#947
Road Division Chapra.
Saran Road Circle Hajipur.
Bihar RCD PMIS — Road Project◐ Ongoning
Agreement₹68.15 Cr
Length31.60 km
Start12-01-2026
Completion11-07-2027
MDR · North Wing
Road Division Chapra.
PALAK MAA JV

Project Details

Project No.947
WingNorth Wing
DivisionRoad Division Chapra.
CircleSaran Road Circle Hajipur.
Road TypeMDR
HeadState Plan

Cost & Timeline

Agreement Value₹68.15 Cr
Sanctioned Length31.60 km
ContractorPALAK MAA JV
AA Date05-02-2025
Start Date12-01-2026
Expected Completion11-07-2027

Remarks

Work in progress. Request letter for NOC of tree Cutting/Translocation has been submitted to DFO, Saran, Chapra EE office letter no.-216, dt.-25.01.2025, lt. no.-351, dt.-11.02.2025, lt. no.-457, dt.-25.02.2025, lt. no.-1423, dt.-28.05.2025, lt. no.- 3036, dt.- 13.12.2025 and Lt. No. 543, dt- 18.02.2026. Re-Joint Tree counting has been done. NOC yet not received. Request letter for NOC for construction of Box Culvert vide this office lt. No.- 3028(We), dt- 12.12.2025 to EE, Canal Division, Chapra. NOC yet not received.

Frequently Asked Questions

What is the current status of the Bihar RCD project "Widening and Strengthening work of Ekma-Masrakh Road from km 0.00 to 31.60 under"?
Status: Ongoning. This MDR project under Road Division Chapra. (Saran Road Circle Hajipur.) covers 31.60 km of road work. Expected completion: 11-07-2027.
Who is the contractor for RCD project 947?
The contractor for this project is PALAK MAA JV. Project number: 947. Division: Road Division Chapra.. Administrative approval date: 05-02-2025.
What is the agreement value for this Bihar road project?
The agreement value for "Widening and Strengthening work of Ekma-Masrakh Road from km" is ₹68.15 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Chapra..
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 947 "Widening and Strengthening work of Ekma-Masrakh Road from km" is one of thousands of road improvement and construction works tracked by BiharInfraTales.
Bihar RCD PMIS Dashboard

Related Resources

RCD

Bihar RCD PMIS Dashboard

All RCD road projects across Bihar

Roads

Bihar Road Network GIS Map

Visual map of Bihar highway and road network

NHAI

NHAI Drone Tracker

National highway drone-monitored progress

BRPNNL

BRPNNL Bridge Projects

Bihar bridge project monitor

Projects

Bihar Infrastructure Projects

All government infrastructure project tracker

Tenders

Bihar Government Tenders

Active procurement notices for road projects

IPM

Central Project Monitor (IPM)

Centrally-funded infrastructure in Bihar

Cabinet

Bihar Cabinet Decisions

Government policy for infrastructure projects

EC

Stage-1 EC Clearances

Forest and environmental clearances

Districts

Bihar District Data

District-level infrastructure and demographics

  1. BiharInfraTales
  2. /RCD PMIS
  3. /Widening and Strengthening work of Ekma-Masrakh Ro