| Project No. | 907 |
| Wing | South Wing |
| Division | Road Division Biharsharif. |
| Circle | Central Road Circle Patna. |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹18.19 Cr |
| Sanctioned Length | 6.00 km |
| Contractor | Balkrishna Bhalotia Const. Pvt. Ltd. |
| AA Date | 28-02-2025 |
| Start Date | 26-02-2026 |
| Expected Completion | 25-02-2027 |
Work is in progress. (Physical work completed - 6%). Site clearance/NOC - 1st stage granted Payment done. Pending at DFO for Compliance Review. Utility Shifting Status - Sanctioned copy of Utility shifting Estimate has received this office dated-12.01.2026.
Superintending Engineer quality visit record
Central Road Circle Patna. · Road Division Biharsharif.
Visited: 27 Jan 2026"Review meeting was Conducted on 27/01/2026. During meeting the condition of the road and ongoing works were reviewed, and necessary observations/instructions were communicated to the Executive Engineer and Contractor."