MDRRCD BiharOngoning

Widening & Improvement to Two Lane with Paved Shoulder from Aryan Mandir to NH-922 Via Ara-Sinha & Ara-Barhara and Link Road From Aryan Devi to Police Line Chowk via Old Po- lice Line, Maula Bagh, Pakri Chowk, Club More with utility shifting for

#877
Road Division Arrah.
Bhojpur Road Circle Arrah.
Bihar RCD PMIS — Road Project◐ Ongoning
Agreement₹24.60 Cr
Length8.82 km
Start27-09-2025
Completion30-11-2026
MDR · South Wing
Road Division Arrah.
Jai Mata Dee and Maa Sita Construction

Project Details

6 Fields
Project No.
877
Wing
South Wing
Division
Road Division Arrah.
Circle
Bhojpur Road Circle Arrah.
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹24.60 Cr
Sanctioned Length
8.82 km
Contractor
Jai Mata Dee and Maa Sita Construction
AA Date
28-02-2025
Start Date
27-09-2025
Expected Completion
30-11-2026

Widening & Improvement to Two Lane with Paved Shoulder from Aryan Mandir to NH-922 Via Ara-Sinha & Ara-Barhara and Link Road From Aryan Devi to Police Line Chowk via Old Po- lice Line, Maula Bagh, Pakri Chowk, Club More with utility shifting for is a Bihar Road Construction Department (RCD) project under Road Division Arrah., classified as a MDR. The agreement amount for this project is ₹24.60 Cr, and the current status is Ongoning.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

EW , GSB WMM work is in progress.

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Widening & Improvement to Two Lane with Paved Shoulder from Aryan Mandir to NH-9"?
Status: Ongoning. This MDR project under Road Division Arrah. (Bhojpur Road Circle Arrah.) covers 8.82 km of road work. Expected completion: 30-11-2026.
QWho is the contractor for RCD project 877?
The contractor for this project is Jai Mata Dee and Maa Sita Construction. Project number: 877. Division: Road Division Arrah.. Administrative approval date: 28-02-2025.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Widening & Improvement to Two Lane with Paved Shoulder from " is ₹24.60 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Arrah..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 877 "Widening & Improvement to Two Lane with Paved Shoulder from " is one of thousands of road improvement and construction works tracked by BiharInfraTales.