MDRRCD BiharCompleted
Balance work (After Work Rescinded vide E.E. Letter no.- 596 dated 11.05.2023) for Widening & Strengthening work including Earth work, Crust work, Box culvert, Utility shifting, Road safety,Miscellaneous work of Hati (SH-56) to Pipra Ghat Road in km 3.950
#835
Road Division Rosera.
Road Circle Darbhanga.
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹6.09 Cr
Length2.25 km
Start14-11-2023
Completion15-07-2024
MDR · North Wing
Road Division Rosera.
Ram Barat Sharma Electric Work Pvt. Ltd.
Project Details
Project No.835
WingNorth Wing
DivisionRoad Division Rosera.
CircleRoad Circle Darbhanga.
Road TypeMDR
HeadState Plan
Cost & Timeline
Agreement Value₹6.09 Cr
Sanctioned Length2.25 km
ContractorRam Barat Sharma Electric Work Pvt. Ltd.
AA Date09-09-2020
Start Date14-11-2023
Expected Completion15-07-2024
Balance work (After Work Rescinded vide E.E. Letter no.- 596 dated 11.05.2023) for Widening & Strengthening work including Earth work, Crust work, Box culvert, Utility shifting, Road safety,Miscellaneous work of Hati (SH-56) to Pipra Ghat Road in km 3.950 is a Bihar Road Construction Department (RCD) project under Road Division Rosera., classified as a MDR. The agreement amount for this project is ₹6.09 Cr, and the current status is **Completed**.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Work Completed
Frequently Asked Questions
- What is the current status of the Bihar RCD project "Balance work (After Work Rescinded vide E.E. Letter no.- 596 dated 11.05.2023) f"?
- Status: Completed. This MDR project under Road Division Rosera. (Road Circle Darbhanga.) covers 2.25 km of road work. Expected completion: 15-07-2024.
- Who is the contractor for RCD project 835?
- The contractor for this project is Ram Barat Sharma Electric Work Pvt. Ltd.. Project number: 835. Division: Road Division Rosera.. Administrative approval date: 09-09-2020.
- What is the agreement value for this Bihar road project?
- The agreement value for "Balance work (After Work Rescinded vide E.E. Letter no.- 596" is ₹6.09 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Rosera..
- What does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 835 "Balance work (After Work Rescinded vide E.E. Letter no.- 596" is one of thousands of road improvement and construction works tracked by BiharInfraTales.