Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
MDRRCD BiharCompleted

Repair and Maintenance of Left out portion of NH-107 at Mathahi between proposed new chainage 84+600 and Ch 86+250 (Total leftout portion length 1.65 Km) under Road Division, Madhepura, for the year-2023-24

#715
Road Division Madhepura.
Road Circle Saharsa
Bihar RCD PMIS — Road ProjectCompleted
Agreement₹2.47 Cr
Length1.65 km
StartN/A
Completion20-01-2025
MDR · Simanchal Wing
Road Division Madhepura.
SINCON INFRASTRUCTURE PRIVATE LIMITED

Project Details

Project No.715
WingSimanchal Wing
DivisionRoad Division Madhepura.
CircleRoad Circle Saharsa
Road TypeMDR
HeadPLAN

Cost & Timeline

Agreement Value₹2.47 Cr
Sanctioned Length1.65 km
ContractorSINCON INFRASTRUCTURE PRIVATE LIMITED
AA Date19-09-2023
Start DateN/A
Expected Completion20-01-2025

Repair and Maintenance of Left out portion of NH-107 at Mathahi between proposed new chainage 84+600 and Ch 86+250 (Total leftout portion length 1.65 Km) under Road Division, Madhepura, for the year-2023-24 is a Bihar Road Construction Department (RCD) project under Road Division Madhepura., classified as a MDR. The agreement amount for this project is ₹2.47 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Work Completed.

Frequently Asked Questions

What is the current status of the Bihar RCD project "Repair and Maintenance of Left out portion of NH-107 at Mathahi between proposed"?
Status: Completed. This MDR project under Road Division Madhepura. (Road Circle Saharsa) covers 1.65 km of road work. Expected completion: 20-01-2025.
Who is the contractor for RCD project 715?
The contractor for this project is SINCON INFRASTRUCTURE PRIVATE LIMITED. Project number: 715. Division: Road Division Madhepura.. Administrative approval date: 19-09-2023.
What is the agreement value for this Bihar road project?
The agreement value for "Repair and Maintenance of Left out portion of NH-107 at Math" is ₹2.47 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Madhepura..
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 715 "Repair and Maintenance of Left out portion of NH-107 at Math" is one of thousands of road improvement and construction works tracked by BiharInfraTales.