MDRRCD BiharCompleted
Construction of Lalganj Bazar Bypass Road in SH-74 from CH-0.00 km to 2.70 km (Total Length 2.70 km) in Vaishali District for the year 2022-23
#637
Road Division Hajipur.
Saran Road Circle Hajipur.
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹12.55 Cr
Length2.73 km
Start14-08-2023
Completion30-06-2025
MDR · North Wing
Road Division Hajipur.
M/S Saran Construction
Project Details
6 FieldsProject No.
637
Wing
North Wing
Division
Road Division Hajipur.
Circle
Saran Road Circle Hajipur.
Road Type
MDR
Head
Bypass
Cost & Timeline
6 FieldsAgreement Value
₹12.55 Cr
Sanctioned Length
2.73 km
Contractor
M/S Saran Construction
AA Date
12-08-2022
Start Date
14-08-2023
Expected Completion
30-06-2025
Construction of Lalganj Bazar Bypass Road in SH-74 from CH-0.00 km to 2.70 km (Total Length 2.70 km) in Vaishali District for the year 2022-23 is a Bihar Road Construction Department (RCD) project under Road Division Hajipur., classified as a MDR. The agreement amount for this project is ₹12.55 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Utility Shifting in Progress
SE Inspection Log
Superintending Engineer quality visit record
Saran Road Circle Hajipur. · Road Division Hajipur.
Visited: 20 Jul 2024"
"Lalganj bazar bypass road"
?
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "Construction of Lalganj Bazar Bypass Road in SH-74 from CH-0.00 km to 2.70 km (T"?
- Status: Completed. This MDR project under Road Division Hajipur. (Saran Road Circle Hajipur.) covers 2.73 km of road work. Expected completion: 30-06-2025.
- QWho is the contractor for RCD project 637?
- The contractor for this project is M/S Saran Construction. Project number: 637. Division: Road Division Hajipur.. Administrative approval date: 12-08-2022.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "Construction of Lalganj Bazar Bypass Road in SH-74 from CH-0" is ₹12.55 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Hajipur..
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 637 "Construction of Lalganj Bazar Bypass Road in SH-74 from CH-0" is one of thousands of road improvement and construction works tracked by BiharInfraTales.