| Project No. | 625 |
| Wing | North Wing |
| Division | Road Division Motihari. |
| Circle | Road Circle Motihari |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹23.95 Cr |
| Sanctioned Length | 1.76 km |
| Contractor | Rishi Builders (I) Pvt. Ltd. |
| AA Date | 27-03-2023 |
| Start Date | 22-09-2023 |
| Expected Completion | 15-12-2025 |
Work completed.
Superintending Engineer quality visit record
Road Circle Motihari · Road Division Motihari.
Visited: 26 Jul 2024"Part-A- in 670m GSB work done. 4 CD Work done. 400m drain & 180m retaining wall work is in progress. Part-B- E/W work is in progress in 350m."