Widening and Strengthening of Lakhisarai (SH-08) to Pachna (SH-18) in Km. 0.00 to 18.60
Project Details
6 FieldsCost & Timeline
6 FieldsWidening and Strengthening of Lakhisarai (SH-08) to Pachna (SH-18) in Km. 0.00 to 18.60 is a Bihar Road Construction Department (RCD) project under Road Division Lakhisarai., classified as a MDR. The agreement amount for this project is ₹48.91 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
1)Total length of the road is 18.6 km 2)11.40 km length of the road is under Road division Lakhisarai 3)Road length 7.20 km is under Road Division Sheikhpura.4)From Chainage 8.24 km to Chainage 15.8 km there is provision of raising. Revise TS has been submited to department for approval of Earth Work shall be used in raising portion. one minor bridge has been complited.
SE Inspection Log
Superintending Engineer quality visit record
Road Circle Munger · Road Division Lakhisarai.
Visited: 12 Jun 2024"पथ प्रमंडल, लखीसराय अन्तर्गत इस पथ का पथांष 0.00 से 11.400 तक है एवं चैनेज 11.400 से 18.600 तक पथ प्रमंडल, शेखपुरा अन्तर्गत है। इस पथ में Ch-000 से Ch-1234 तक PQC कार्य पूर्ण करा लिया गया है। Flank निर्माण का कार्य प्रगति पर है। पथ के Ch-2.200(RUB) में PQC कार्य प्रगति पर है। Ch-1230 से Ch-6000 में Widening में GSB कार्य करा लिया गया है। Flank में मिट्टी कार्य किया जा रहा है। Ch-6.00 से Ch-8.20 में Scarifying का कार्य एवं Widening में Box Cutting कार्य प्रगति पर है। Ch-8.20 से Ch-11.4 तक Scarifying का कार्य किया जा रहा है। इस पथ में कुल दो अदद् Box Culvert का निर्माण प्रगति पर है। तीन अदद् Box Culvert का निर्माण पूर्ण करा लिया गया है। Ch-5.60 से Ch-6.15 एवं Ch-10.100 से Ch-10.500 तक PQC कार्य पूर्ण करा लिया गया एवं Shoulder का निर्माण किया जा रहा है। पथ प्रमंडल, शेखपुरा अन्तर्गत Ch-11.40 से Ch-18.60 तक में कुल चार अदद् Box Culvert का निर्माण पूर्ण करा लिया गया है। चार अदद् Box Culvert एवं एक Minor Bridge का निर्माण कार्य प्रगति पर है।"
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "Widening and Strengthening of Lakhisarai (SH-08) to Pachna (SH-18) in Km. 0.00 t"?
- Status: Completed. This MDR project under Road Division Lakhisarai. (Road Circle Munger) covers 18.60 km of road work. Expected completion: 31-03-2027.
- QWho is the contractor for RCD project 616?
- The contractor for this project is M/S Ramjee Singh Co.Pvt. Ltd. Project number: 616. Division: Road Division Lakhisarai.. Administrative approval date: 30-07-2023.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "Widening and Strengthening of Lakhisarai (SH-08) to Pachna (" is ₹48.91 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Lakhisarai..
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 616 "Widening and Strengthening of Lakhisarai (SH-08) to Pachna (" is one of thousands of road improvement and construction works tracked by BiharInfraTales.