MDRRCD BiharCompleted

Widening and strengthning work of new siwan - hasua road ( ch 4.33km to 14.25 km) total length 9.92 km for the year 2022-23

#615
Road Division Siwan.
Saran Road Circle Hajipur.
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹28.02 Cr
Length9.92 km
Start04-09-2023
Completion03-09-2024
MDR · North Wing
Road Division Siwan.
Balwant Const Pvt. Ltd.

Project Details

6 Fields
Project No.
615
Wing
North Wing
Division
Road Division Siwan.
Circle
Saran Road Circle Hajipur.
Road Type
MDR
Head
PLAN

Cost & Timeline

6 Fields
Agreement Value
₹28.02 Cr
Sanctioned Length
9.92 km
Contractor
Balwant Const Pvt. Ltd.
AA Date
27-03-2023
Start Date
04-09-2023
Expected Completion
03-09-2024

Widening and strengthning work of new siwan - hasua road ( ch 4.33km to 14.25 km) total length 9.92 km for the year 2022-23 is a Bihar Road Construction Department (RCD) project under Road Division Siwan., classified as a MDR. The agreement amount for this project is ₹28.02 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Project complete

SE Inspection Log

Superintending Engineer quality visit record

Saran Road Circle Hajipur. · Road Division Siwan.

Visited: 23 Dec 2023
"

"Work is in Progress"

Inspection Report PDF
?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Widening and strengthning work of new siwan - hasua road ( ch 4.33km to 14.25 km"?
Status: Completed. This MDR project under Road Division Siwan. (Saran Road Circle Hajipur.) covers 9.92 km of road work. Expected completion: 03-09-2024.
QWho is the contractor for RCD project 615?
The contractor for this project is Balwant Const Pvt. Ltd.. Project number: 615. Division: Road Division Siwan.. Administrative approval date: 27-03-2023.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Widening and strengthning work of new siwan - hasua road ( c" is ₹28.02 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Siwan..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 615 "Widening and strengthning work of new siwan - hasua road ( c" is one of thousands of road improvement and construction works tracked by BiharInfraTales.