Strengthening work in km 0.00 to 21.00 km of Ara (NH-30) to Chapra (NH-19) vai Babura, Doriganj Road for the year 2022-23
Project Details
6 FieldsCost & Timeline
6 FieldsStrengthening work in km 0.00 to 21.00 km of Ara (NH-30) to Chapra (NH-19) vai Babura, Doriganj Road for the year 2022-23 is a Bihar Road Construction Department (RCD) project under Road Division Arrah., classified as a MDR. The agreement amount for this project is ₹74.23 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Work is in progress.LD imposed-95.49534 lacs vide EE letter no 2435 Dated 26-12-2024.PQC work completed.DBM-16km BC-16 km
SE Inspection Log
Superintending Engineer quality visit record
Bhojpur Road Circle Arrah. · Road Division Arrah.
Visited: 5 Sept 2024"इस पथ की कुल लम्बाई 21.00 कि0मी0 है, चौड़ाई 2x7.5M है । यह पथ संवेदक मेसर्स एस० एवं पी० इन्फ्रास्ट्रक्चर डेभलपरर्स प्रा० लि0, 907 New Delhi house 27, Barakhamba Road, New Delhi-110001 को आवंटित किया गया है। जिसकी एकरारनामा की राशि :- 74,23,30,428,00 है। कार्यदेश की तिथि :- 16.08.2023 को निर्गत किया गया है। कार्य समाप्ति की तिथि 15.02.2025 ( 18 माह ) है । संवेदक द्वारा कार्य कार्यक्रम (Work Program) भी दिया गया है। निरीक्षण के समय पथ के Left side पथ में Scarifying (Cold milling machines) का कार्य कि०मी० 1.00 से 14.00 कि०मी० तक लगभग पूर्ण किया पाया गया है। 14 वें कि०मी० में Scarifying कार्य किया जा रहा है एवं DLC 10.0km एवं PQC-8.5km लगभग पूर्ण पाया गया । कार्य की प्रगति धीमी है। कार्य योजना (Work Program) के अनुरूप कार्य संतोष जनक नहीं पाया गया है। Quality Control से संबंधित Lab कैम्प में स्थापित पाया गया है। पथ निर्माण कार्य से संबंधित सूचना पट्ट नहीं पाया गया। कार्यपालक अभियंता तथा संवेदक को प्रथम एवं अंतिम कि०मी० में Informatory Board लगाने का निदेश दिया गया। कार्यपालक अभियंता को निदेशित किया गया है कि उक्त कार्य में तेजी लाकर यथाशीघ्र कार्य पूर्ण करना सुनिश्चित की जाय ।"
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "Strengthening work in km 0.00 to 21.00 km of Ara (NH-30) to Chapra (NH-19) vai B"?
- Status: Completed. This MDR project under Road Division Arrah. (Bhojpur Road Circle Arrah.) covers 21.00 km of road work. Expected completion: 25-12-2025.
- QWho is the contractor for RCD project 590?
- The contractor for this project is S& P Infra Structrure Developers Pvt. Ltd.. Project number: 590. Division: Road Division Arrah.. Administrative approval date: 27-03-2023.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "Strengthening work in km 0.00 to 21.00 km of Ara (NH-30) to " is ₹74.23 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Arrah..
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 590 "Strengthening work in km 0.00 to 21.00 km of Ara (NH-30) to " is one of thousands of road improvement and construction works tracked by BiharInfraTales.