| Project No. | 575 |
| Wing | Simanchal Wing |
| Division | Road Division Kishanganj. |
| Circle | Road Circle Purnea |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹22.08 Cr |
| Sanctioned Length | 5.95 km |
| Contractor | M/S Sanatlall & Brothers |
| AA Date | 17-03-2022 |
| Start Date | 04-11-2022 |
| Expected Completion | 11-11-2024 |
1. DBM and BC work Pending in approach of one Culvert (Total Length including both side approach is approx. 100m), 2. Earthen shoulder work in 1.5 m width has been completed before rainy season due to unavailabilety of soil in rainy season, remaining 0.5m shoulder work shall be completed after rainy season. 3. Contractor is debarred due to delay in Completion.
Superintending Engineer quality visit record
Road Circle Purnea · Road Division Kishanganj.
Visited: 24 Sept 2024"Box culvert के दोनों तरफ पहुँच पथ लगभग 100 m में 15 दिनों के अन्दर Bituminous कार्य पूर्ण कराने का निदेश दिया गया"