MDRRCD BiharCompleted
Widening & Strengthening of Badhibagh – Charkapathar – Gaganpur Road Chanage (KM 20+000 to 39+880) (Part-B, Package No-BR15RC205) under RCPLWE for the year 2019-20 (Agreement No.- 29/RCPCWEA/2020-21)
#411
Road Division Jamui
Road Circle Munger
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹19.08 Cr
Length19.88 km
Start21-01-2021
Completion20-07-2022
MDR · South Wing
Road Division Jamui
RAJEEV KUMAR
Project Details
6 FieldsProject No.
411
Wing
South Wing
Division
Road Division Jamui
Circle
Road Circle Munger
Road Type
MDR
Head
State Plan
Cost & Timeline
6 FieldsAgreement Value
₹19.08 Cr
Sanctioned Length
19.88 km
Contractor
RAJEEV KUMAR
AA Date
31-08-2020
Start Date
21-01-2021
Expected Completion
20-07-2022
Widening & Strengthening of Badhibagh – Charkapathar – Gaganpur Road Chanage (KM 20+000 to 39+880) (Part-B, Package No-BR15RC205) under RCPLWE for the year 2019-20 (Agreement No.- 29/RCPCWEA/2020-21) is a Bihar Road Construction Department (RCD) project under Road Division Jamui, classified as a MDR. The agreement amount for this project is ₹19.08 Cr, and the current status is Completed.
RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.
Remarks
Road Length= 19.880 km excuted as dropped by Joint Director(Technical), NRIDA (ministry of Rural Development Govt. of India) vide DO No. NRRDA-P017(23)/6/2025-Dir(Tech) (E: 393935)/1466, dt.- 22.12.2025
?
Frequently Asked Questions
- QWhat is the current status of the Bihar RCD project "Widening & Strengthening of Badhibagh – Charkapathar – Gaganpur Road Chanage (KM"?
- Status: Completed. This MDR project under Road Division Jamui (Road Circle Munger) covers 19.88 km of road work. Expected completion: 20-07-2022.
- QWho is the contractor for RCD project 411?
- The contractor for this project is RAJEEV KUMAR. Project number: 411. Division: Road Division Jamui. Administrative approval date: 31-08-2020.
- QWhat is the agreement value for this Bihar road project?
- The agreement value for "Widening & Strengthening of Badhibagh – Charkapathar – Gagan" is ₹19.08 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Jamui.
- QWhat does RCD PMIS track in Bihar?
- Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 411 "Widening & Strengthening of Badhibagh – Charkapathar – Gagan" is one of thousands of road improvement and construction works tracked by BiharInfraTales.