MDRRCD BiharCompleted

Work Completed

#242
Road Division Sitamarhi.
North Bihar Road Circle Muzaffarpur
Bihar RCD PMIS — Road Project✓ Completed
Agreement₹14.03 Cr
Length4.80 km
Start05-07-2021
Completion31-03-2023
MDR · North Wing
Road Division Sitamarhi.
M/s Kabbu Khirhar

Project Details

6 Fields
Project No.
242
Wing
North Wing
Division
Road Division Sitamarhi.
Circle
North Bihar Road Circle Muzaffarpur
Road Type
MDR
Head
State Plan

Cost & Timeline

6 Fields
Agreement Value
₹14.03 Cr
Sanctioned Length
4.80 km
Contractor
M/s Kabbu Khirhar
AA Date
01-09-2020
Start Date
05-07-2021
Expected Completion
31-03-2023

Work Completed is a Bihar Road Construction Department (RCD) project under Road Division Sitamarhi., classified as a MDR. The agreement amount for this project is ₹14.03 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Work Completed.

?

Frequently Asked Questions

QWhat is the current status of the Bihar RCD project "Work Completed"?
Status: Completed. This MDR project under Road Division Sitamarhi. (North Bihar Road Circle Muzaffarpur) covers 4.80 km of road work. Expected completion: 31-03-2023.
QWho is the contractor for RCD project 242?
The contractor for this project is M/s Kabbu Khirhar. Project number: 242. Division: Road Division Sitamarhi.. Administrative approval date: 01-09-2020.
QWhat is the agreement value for this Bihar road project?
The agreement value for "Work Completed" is ₹14.03 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Sitamarhi..
QWhat does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 242 "Work Completed" is one of thousands of road improvement and construction works tracked by BiharInfraTales.