| Project No. | 241 |
| Wing | North Wing |
| Division | Road Division Sitamarhi. |
| Circle | North Bihar Road Circle Muzaffarpur |
| Road Type | MDR |
| Head | State Plan |
| Agreement Value | ₹74.21 Cr |
| Sanctioned Length | 29.34 km |
| Contractor | M/s Kabbu Khirhar |
| AA Date | 01-09-2020 |
| Start Date | 12-06-2021 |
| Expected Completion | 31-05-2024 |
Work Completed. only 40 meter PQC is left due to dispute of land. Letter of descope of work has been sent to S.E, NBC, Muzaffarpur vide letter no.-1032 (E) dt. 04.07.2024 (i) Delay due to heavy rainfall (ii) The work delay due to NOC not given in time by water resource department for construction of bituminous road in total length 2175m from CH-17.90 to 20.075 of Sandhwara Bay embankment. (iii) In this work extra 2.335 km. road length along with culvert and bridges is to be constructed due to revised TS given by the department on dt. 24.08.2022, So extra time is required for the construction of additional work.
Superintending Engineer quality visit record
North Bihar Road Circle Muzaffarpur · Road Division Sitamarhi.
Visited: 19 Feb 2024"PQC WORK 350M LEFT.4 NOS OF HL BRIDGE CONSTRUCTED.APPROACH OF ONE HL BRIDGE UNDER PROGRESS.10NOS OF BOX CULVERT CONSTRUCTED"