Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
MDRRCD BiharCompleted

Balance Work of CMBD Based road contract for the construction & maintenance of Biroul Singhia via Pipara Road (Singhia - Hirni Road)

#22
Road Division Benipur.
Road Circle Darbhanga.
Bihar RCD PMIS — Road ProjectCompleted
Agreement₹6.99 Cr
Length3.10 km
Start25-06-2020
Completion24-12-2020
MDR · North Wing
Road Division Benipur.
Keshav Contractor Pvt. Ltd.

Project Details

Project No.22
WingNorth Wing
DivisionRoad Division Benipur.
CircleRoad Circle Darbhanga.
Road TypeMDR
HeadState Plan

Cost & Timeline

Agreement Value₹6.99 Cr
Sanctioned Length3.10 km
ContractorKeshav Contractor Pvt. Ltd.
AA Date22-12-2016
Start Date25-06-2020
Expected Completion24-12-2020

Balance Work of CMBD Based road contract for the construction & maintenance of Biroul Singhia via Pipara Road (Singhia - Hirni Road) is a Bihar Road Construction Department (RCD) project under Road Division Benipur., classified as a MDR. The agreement amount for this project is ₹6.99 Cr, and the current status is Completed.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Work Completed

Frequently Asked Questions

What is the current status of the Bihar RCD project "Balance Work of CMBD Based road contract for the construction & maintenance of B"?
Status: Completed. This MDR project under Road Division Benipur. (Road Circle Darbhanga.) covers 3.10 km of road work. Expected completion: 24-12-2020.
Who is the contractor for RCD project 22?
The contractor for this project is Keshav Contractor Pvt. Ltd.. Project number: 22. Division: Road Division Benipur.. Administrative approval date: 22-12-2016.
What is the agreement value for this Bihar road project?
The agreement value for "Balance Work of CMBD Based road contract for the constructio" is ₹6.99 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Benipur..
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 22 "Balance Work of CMBD Based road contract for the constructio" is one of thousands of road improvement and construction works tracked by BiharInfraTales.