Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
MDRRCD BiharCompleted

CMBD Based work for Widening & Strengthening of Chanderdai-Bangama-Paiktola-Matiyari-Mogra Road (km 1st, 11p, 12, 13, 14p, 15p, 16 to 24, 25p, 26p 27 & 28)

#191
Road Division Araria.
Road Circle Purnea
Bihar RCD PMIS — Road ProjectCompleted
Agreement₹36.95 Cr
Length14.83 km
Start27-06-2018
Completion30-06-2023
MDR · Simanchal Wing
Road Division Araria.
RKS Engicon Pvt.Ltd.

Project Details

Project No.191
WingSimanchal Wing
DivisionRoad Division Araria.
CircleRoad Circle Purnea
Road TypeMDR
HeadState Plan

Cost & Timeline

Agreement Value₹36.95 Cr
Sanctioned Length14.83 km
ContractorRKS Engicon Pvt.Ltd.
AA Date09-10-2017
Start Date27-06-2018
Expected Completion30-06-2023

CMBD Based work for Widening & Strengthening of Chanderdai-Bangama-Paiktola-Matiyari-Mogra Road (km 1st, 11p, 12, 13, 14p, 15p, 16 to 24, 25p, 26p 27 & 28) is a Bihar Road Construction Department (RCD) project under Road Division Araria., classified as a MDR. The agreement amount for this project is ₹36.95 Cr, and the current status is **Completed**.

RCD projects like this form part of Bihar's state highway and rural road network expansion. Other road projects under the same division are listed below.

Remarks

Construction work completed on 30.06.2023. CMBD Project (under Maintenance)

Frequently Asked Questions

What is the current status of the Bihar RCD project "CMBD Based work for Widening & Strengthening of Chanderdai-Bangama-Paiktola-Mati"?
Status: Completed. This MDR project under Road Division Araria. (Road Circle Purnea) covers 14.83 km of road work. Expected completion: 30-06-2023.
Who is the contractor for RCD project 191?
The contractor for this project is RKS Engicon Pvt.Ltd.. Project number: 191. Division: Road Division Araria.. Administrative approval date: 09-10-2017.
What is the agreement value for this Bihar road project?
The agreement value for "CMBD Based work for Widening & Strengthening of Chanderdai-B" is ₹36.95 Cr. This is a MDR project under Bihar Roads Construction Department (RCD) in Road Division Araria..
What does RCD PMIS track in Bihar?
Bihar RCD (Road Construction Department) PMIS (Project Management Information System) tracks state highway, major district road, and rural road construction projects across Bihar. Project 191 "CMBD Based work for Widening & Strengthening of Chanderdai-B" is one of thousands of road improvement and construction works tracked by BiharInfraTales.